Longjobs project status report

daemon@ATHENA.MIT.EDU (Robert A Basch)
Tue Jul 24 18:59:03 2001

Message-Id: <200107242259.SAA00783@anhedonia.mit.edu>
To: magellan@MIT.EDU
Date: Tue, 24 Jul 2001 18:59:00 -0400
From: Robert A Basch <rbasch@MIT.EDU>

Project Name: Longjobs
Project Leader: Robert Basch
Report Date: July 24, 2001
URL: http://web.mit.edu/longjobs/


Recent accomplishments:

- Prepared a report on the results of the spring term test.

- Recommended continuing the test in the fall, since the spring load
  was less than we expected.

- Prepared a list of potential remaining development tasks.

- Began recruitment of testers for the fall; two classes are lined up
  so far.

- Ported code to Athena 9.0 (Solaris 8, Redhat 7.1), and began
  testing.

- Discussed possible ways to address the temporary disk space issues.

- Set up new machines for debugging.


Upcoming plans:

- Recruit testers for fall.

- Test software under Athena 9.0.

- Schedule update of test machines.

- Investigate getting a Moira feed for doing group membership lookup.

- Further investigation of temp disk space issues.

- Update project notebook.

- Update documentation.


Issues:

- Faculty from the spring test don't teach classes that can make use
  of it in the fall, so probably we will need to recruit an entirely
  new set of testers.