Project Name: Pismere Business Models
Project Leader Greg Anderson, Jonathan Venezian
Report Date Feb. 12, 1999
URL: http://mit.edu/pismere/business/business.html
Accomplishments past period
- Met with Jonathan Venezian
- Developed rough workplan
- Began planning for initial kick-off
- Continued recruiting efforts for team
- Updated project-db
Goals for the coming period
- Hold kick-off meeting
- Begin data gathering
- Continue team recruiting
Issues
- Scheduling the meeting
- Relationship of this project with the new staff vacancy now posted; will
the new staff member be on board in a timely manner.
- Staffing remains a problem - Finance team is spread thin
Key learnings
- There's a fragile balance between moving forward and alignment.
Team dynamics:
- Not up an running yet.
Additional comments:
- None