Project Name: Office of Corporate Relations (OCR)
Project Leader: Esther Yanow
Report Date: February 11, 1999
Accomplishments past period:
- The OCR team reconvened and met on January 28, 1999.
- Reviewed our high-level requirements and functional specifications.
- Sue Shansky, Director of Operations, met with her OCR directors and
brought them up-to-date on our activities.
- Gave all our current documents to Scott Thorne for his review and
requested his assistance in helping the group create a data model for the
new system.
Goals for the coming period: The time span will cover more than just the
coming period.
1. List the functional requirements.----Done
2. Invite Scott Thorne to a meeting and ask his help in creating a data
model.---We are now (2/10/1999) at this point. Scott will discuss the
process with Greg and me before he presents his information to the OCR
group.
3. Show the data model to Susan Minai Azary.
4. Invite Brenda Gillingham or Joanne Hallisey to help write an RFP.
5. Show the vendor responses to the Integration Group and ask them to
advise in the group's choice of a vendor.
6. Ask Greg or Scott (or anyone else who can help) to check on other
existing systems at MIT that might have some of the features we're looking
for.
Issues: None
Key learnings: None
Team dynamics: None
Additional comments: None