Project Name:      Class Participants Lists
Project Leaders:   Tim McGovern
Report Date:       February 16, 2000
Project Notebooks: http://mit.edu/is/discovery/grouper/ &
		   http://mit.edu/is/delivery/grouper/

Goals listed in last report
1  Meet with IS project sponsor
2  Attempt to determine where the Moira development -> operations situation is
3  Schedule final meeting (approx. mid-February) and celebration for project.

Accomplishments past period
-  Met with IS project sponsor, who concurred with the sense that, Moira
   production turnover notwithstanding, we're ready to declare the Delivery
   project completed.
-  No progress on assessment of Moira development -> operations situation
-  No progress on scheduling final meeting (approx. mid-February)/celebration.

Goals for the coming period (or so)

-  Continue with carryover goals from last report.

Issues
-  None

Key learnings
-  None

Team dynamics
-  None

Additional comments
-  None