[396] in magellan
IS Operational Plan Alive, February 16, 2000
daemon@ATHENA.MIT.EDU (Tim McGovern)
Wed Feb 16 16:36:40 2000
Mime-Version: 1.0
Content-Type: text/plain; charset="us-ascii"
Message-Id: <v04020a10b4d0c8704278@[18.152.1.21]>
Date: Wed, 16 Feb 2000 16:36:36 -0500
To: magellan@MIT.EDU
From: Tim McGovern <tjm@MIT.EDU>
Cc: iswork@MIT.EDU
Project Name: IS Operational Plan Alive!
Project Leaders: Tim McGovern
Report Date: February 16, 2000
Project Notebook: http://web.mit.edu/is/discovery/iswork/
Goals listed in last report
1 Continue modeling efforts, and documenting same.
2 Finalize documentation of business processes.
3 Document effort estimates for delivery work.
4 Prepare for ITLT checkout session.
Accomplishments past period
- Completed all goals in last report, presented plan to ITLT and have
received the go-ahead on Delivery effort, and a commitment to
accomplish the business changes needed to make the Delivery
products effective.
Goals for the coming period (or so)
*** Discovery Work has been Completed ***
Issues
- None
Key learnings
- None
Team dynamics
- None
Additional comments
- None