Scopus Status Report 9/06/96

daemon@ATHENA.MIT.EDU (Steven Wade Neiterman)
Tue Sep 10 09:31:32 1996

Date: Tue, 10 Sep 1996 09:32:38 +0100
To: tooltime@MIT.EDU
From: wade@MIT.EDU (Steven Wade Neiterman)


Scopus Implementation
Date: September 06,1996


Working On Milestone:

-  Beta phase continues with multiple releases, testing, and assessment
   of work required to complete this phase.

-  Acceptance testing (1.0b5 release) to be conducted the week September 9th.
   Goal is to conclude the beta phase and to begin a short release phase.

Accomplishments:

-  Completed testing on release 1.0b4
-  Determined minimal changes required for 1.0b5, added summary search (9/5)
-  Completed first (8/29) and second drafts (9/6) of training document
-  Prepared production machine (8/29) for Oracle, space planning completed
-  Installed Oracle 7.1.6 on production machine (9/6)
-  Follow-up on Scopus issues (Mac, InformTEAM), waiting for response
-  Prepared new legacy data (Filemaker) for import into Oracle

Goals:

-  Release 1.0b5 on 9/9 (complete database changes, searching, test)
-  Prepare for student testing: review accounts, reload data
-  Conduct staff and student testing 9/10
-  Conduct testing feedback session
-  Release final "beta" version of training document
-  Continue with post Oracle tasks on production machine
-  Plan date for export/import of data from test to production
-  Continue (complete?) programmers documentation
-  Revise rollout schedule

Issues:

-  Outstanding Macintosh problems, Scopus duplicated problem against our
   database.  Waiting for a reply.  Sent mail on August 7, received reply
   that engineering is aware of problems, no new information.  Issues
   numbers are: 11337 (characters disappear in child entry fields),
   11338 (sorting column headings of result sets), 11339 (printing issue).
   --> Latest update is three week response for fix.

-  InformTEAM (for generation of automated business rules) needs problem
   resolution.  Mail sent to Scopus (8/29), need follow up.

-  SNS may be delayed - checking into Windows 95 issues.

Notes:

-  The week of September 9 - 13 is pivotal for making a decision on
   deployment.  Acceptance testing will have been completed and the
   production machine should be ready to accommodate a transfer of
   data from test.  If both of these items go well, we should have
   enough information to base a decision on a release date.