[210] in Tooltime
Help Desk application schedule
daemon@ATHENA.MIT.EDU (Steven Wade Neiterman)
Mon Aug 26 11:46:57 1996
Date: Mon, 26 Aug 1996 11:47:48 +0100
To: tooltime@MIT.EDU
From: wade@MIT.EDU (Steven Wade Neiterman)
Schedule for review during tooltime meeting on 8/27. Please review and
prepare any comments/changes.
------------------------------------------------------------------------
Mon Aug 26 Tooltime team complete testing 1.0b4
team-usa: Complete install Solaris 2.5
Tue Aug 27 Tooltime meeting, discuss testing, resolve design issues
Make change for history searching based on design resolution
team-usa: RAID configuration complete
Wed Aug 28 Continue with documentation
team-usa: login to machine, begin Oracle install
11:00 am Meeting with database services
Thu Aug 29 End of day completion of training document - first draft
Fri Aug 30 Oracle install completion
------------------------------------------------------------------------
Mon Sep 2 Holiday
Tue Sep 3 Tooltime meeting, review migration and contingency planning
Wed Sep 4 End of day completion of second training draft document
Thu Sep 5 Review training document
Import/Export Oracle data/Scopus from help-them to team-usa
Fri Sep 6 End of day completion of training document for 9/9 release
Produce 1.0b5 for release
11:00 am Peter L. and Wade meet to load Filemaker data
------------------------------------------------------------------------
Mon Sep 9 Tooltime staff and student testing begins on 1.0b5
Tue Sep 10 10:00 am Tooltime meeting, review deployment issues
5:00 pm student testing for stress, acceptance
Wed Sep 11 2:00 pm testing closes
Thu Sep 12 Review testing comments, begin assesment for team meeting
Fri Sep 13 Tooltime meeting to review and make go/no deployment decision
------------------------------------------------------------------------
Mon Sep 14 Make final changes, if any
Tue Sep 15
Wed Sep 16
Thu Sep 17
Fri Sep 18 Production rollout (proposed, earlier if possible)