Bldg. 1 - Chilled Water Shutdown Request

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Mon Aug 5 14:25:56 2002

Message-ID: <568F0AEE7A57D511923900508B55645101232405@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'patdixon@mit.edu'" <patdixon@mit.edu>,
        "'shutdowns@mit.edu'"
	 <shutdowns@mit.edu>,
        "'schedule@mit.edu'" <schedule@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Mon, 5 Aug 2002 14:25:52 -0400 
MIME-Version: 1.0
Content-Type: text/plain

> To: 	patdixon@mit.edu; shutdowns@mit.edu; schedule@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldg. 1 - Chilled Water Shutdown Request
> 
> 
The following chilled water shutdown request for Bldg. 1 - 170 through 190
on Tuesday, 8/6 is for your review and comment.  Would you please let me
know whether this does or does not meet with your approval.

Thank you.

Andrea Nichols
Repair and Maintenance
8-7872

> Status: Normal
> Building: 1 - 170 through 190
> Date: 8/6/2002
> Day: Tuesday
> Time: 7 AM - 11 AM
> System: Chilled Water
> Duration: 4 hours
> Reason: 
> Tie-in new fan coil  unit in 1-179.
> 
> Effect: 
> Loss of chilled water (air conditioning) in 1-170 through 190 during the
> 4-hour shutdown period.
> 
> 
> 
> 
> 
> 