[60640] in Hotline Meeting
Bldg. E25 - Critical Air Handler 1 Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Mon Aug 5 14:28:42 2002
Message-ID: <568F0AEE7A57D511923900508B55645101232406@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'andrea@psyche.mit.edu'" <andrea@psyche.mit.edu>,
"'arolle@mit.edu'"
<arolle@mit.edu>,
"'bengel@mit.edu'" <bengel@mit.edu>,
"'brig@med.mit.edu'" <brig@med.mit.edu>,
"'cpoon@mit.edu'"
<cpoon@mit.edu>, "'dreid@mit.edu'" <dreid@mit.edu>,
E-Zone
<E-Zone@mit.edu>, "'elworthi@mit.edu'" <elworthi@mit.edu>,
"'graposa@MIT.EDU'" <graposa@mit.edu>,
"'hegarty@mit.edu'"
<hegarty@mit.edu>,
"'jmganno@mit.edu'" <jmganno@mit.edu>,
"'jrauch@mit.edu'" <jrauch@mit.edu>,
"'loudib@mit.edu'" <loudib@mit.edu>,
"'mjudge@mit.edu'" <mjudge@mit.edu>, "'rfink@mit.edu'" <rfink@mit.edu>,
"'schedule@mit.edu'" <schedule@mit.edu>,
"'sdalton@mit.edu'"
<sdalton@mit.edu>,
"'sdl-adm-lib@mit.edu'" <sdl-adm-lib@mit.edu>,
"'shyoung@mit.edu'" <shyoung@mit.edu>,
"'tquinn@mit.edu'"
<tquinn@mit.edu>,
"'shutdowns@mit.edu'" <shutdowns@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Mon, 5 Aug 2002 14:28:38 -0400
MIME-Version: 1.0
Content-Type: text/plain
> To: andrea@psyche.mit.edu; arolle@mit.edu; bengel@mit.edu;
> brig@med.mit.edu; cpoon@mit.edu; dreid@mit.edu; E-Zone; elworthi@mit.edu;
> graposa@MIT.EDU; hegarty@mit.edu; jmganno@mit.edu; jrauch@mit.edu;
> loudib@mit.edu; mjudge@mit.edu; rfink@mit.edu; schedule@mit.edu;
> sdalton@mit.edu; sdl-adm-lib@mit.edu; shyoung@mit.edu; tquinn@mit.edu;
> shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. E25 - Critical Air Handler 1 Shutdown Request
>
>
The following Critical Air Handler 1 shutdown request for Blg E25 -
Northeast Labs - floors 2 through 6 on Wednesday, August 7 is for your
information and comment. Would you please let me know whether this does or
does not meet with your approval.
Thank you.
Andrea Nichols
Repair and Maintenance
8-7872
> Status: Critical
> Building: E25 - Northeast Labs - Floors 2 thru 6
> Date: 8/7/2002
> Day: Wednesday
> Time: 7 AM - 9 AM
> System: Air Handler 1
> Duration: 2 hours
> Reason:
> Cleaning of outside air intake screens for improved air flow.
>
> Effect:
> Loss of supply ventilation in the above-mentioned area during the 2-hour
> shudown period.
>
>