[60638] in Hotline Meeting
Bldg. N42 - Emergency Air Handler 2 Shutdown
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Mon Aug 5 13:11:50 2002
Message-ID: <568F0AEE7A57D511923900508B55645101232402@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: D-Zone <D-Zone@MIT.Edu>, "'jean@mit.edu'" <jean@MIT.Edu>,
"'kathyb@mitvmc.mit.edu'" <kathyb@mitvmc.mit.edu>,
"'lgross@mit.edu'"
<lgross@MIT.Edu>,
"'n42site@mit.edu'" <n42site@MIT.Edu>,
"'shutdowns@mit.edu'" <shutdowns@MIT.Edu>,
"'rkedian@mit.edu'"
<rkedian@MIT.Edu>,
"'ganderso@mit.edu'" <ganderso@MIT.Edu>,
"'dcosta@mit.edu'" <dcosta@MIT.Edu>,
"'johnnyd@mit.edu'"
<johnnyd@MIT.Edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>,
"'rm-shutdown@mit.edu'" <rm-shutdown@MIT.Edu>,
Operators
<Operators@PLANT.MIT.EDU>
Date: Mon, 5 Aug 2002 13:11:46 -0400
MIME-Version: 1.0
Content-Type: text/plain
> To: D-Zone; jean@mit.edu; kathyb@mitvmc.mit.edu; lgross@mit.edu;
> n42site@mit.edu; shutdowns@mit.edu; rkedian@mit.edu; ganderso@mit.edu;
> dcosta@mit.edu; johnnyd@mit.edu
> Cc: shutdown@plant.mit.edu; rm-shutdown@mit.edu; Operators
> Subject: Bldg. N42 - Emergency Air Handler 2 Shutdown
>
>
The following emergency Air Handler 2 shutdown for Bldg. N42 - 2nd floor on
Tuesday, August 6 is for your information. If you have any questions about
this, please contact Warren Scott at x3-6328.
Thank you.
Andrea Nichols
Repair and Maintenance
8-7872
> Status: Emergency
> Building: N42 - 2nd floor
> Date: 8/6/2002
> Day: Tuesday
> Time: 7:30 AM - 8:30 AM
> System: Air Handler 2
> Duration: 1 hour
> Reason:
> Repair split duct work.
>
> Effect:
> Loss of supply ventilation and supply cooling in N42 - 2nd floor during
> the 1-hour emergency shutdown period.
>
>