Bldg. E51 - Air Handler 1 Shutdown Request

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu May 10 12:49:22 2001

Message-ID: <82F0D564C5ADD31180EF00508B556451BD2411@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'cbates@mit.edu'" <cbates@mit.edu>, E-Zone <E-Zone@mit.edu>,
        "'graham@mit.edu'" <graham@mit.edu>, "'gwj@mit.edu'" <gwj@mit.edu>,
        "'lhill@mit.edu'" <lhill@mit.edu>, "'mchin@mit.edu'" <mchin@mit.edu>,
        "'mdimauro@mit.edu'" <mdimauro@mit.edu>,
        "'mscoppa@mit.edu'"
	 <mscoppa@mit.edu>,
        "'schedule@mit.edu'" <schedule@mit.edu>,
        "'scobb@mit.edu'" <scobb@mit.edu>,
        "'shutdowns@mit.edu'"
	 <shutdowns@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Thu, 10 May 2001 12:49:11 -0400
MIME-Version: 1.0
Content-Type: text/plain

> To: 	cbates@mit.edu; E-Zone; graham@mit.edu; gwj@mit.edu; lhill@mit.edu;
> mchin@mit.edu; mdimauro@mit.edu; mscoppa@mit.edu; schedule@mit.edu;
> scobb@mit.edu; shutdowns@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldg. E51 - Air Handler 1 Shutdown Request
> 
> 
The following Air Handler 1 shutdown request for Bldg. E51 - West half of
the building on Tuesday, May 15 is for your information and comment.  Would
you please let me know whether this does or does not have your approval.

Thanks very much,

Andrea Nichols
Operations Center
8-7872

> Status: Normal
> Building: E51 - West Half of the Building
> Date: 5/15/2001
> Day: Tuesday
> Time: 2 PM - 6 PM
> System: Air Handler 1
> Duration: 4 hours
> Reason: 
> To free up inlet vanes.
> 
> Effect: 
> Loss of supply ventilation, supply cooling, supply heating and exhaust
> general air during the 4-hour shutdown period.
> 
> 