Bldg. E51 Air Handler 2 Shutdown Request

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu May 10 12:44:31 2001

Message-ID: <82F0D564C5ADD31180EF00508B556451BD2410@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'cbates@mit.edu'" <cbates@mit.edu>, E-Zone <E-Zone@mit.edu>,
        "'graham@mit.edu'" <graham@mit.edu>, "'gwj@mit.edu'" <gwj@mit.edu>,
        "'lhill@mit.edu'" <lhill@mit.edu>, "'mchin@mit.edu'" <mchin@mit.edu>,
        "'mdimauro@mit.edu'" <mdimauro@mit.edu>,
        "'mscoppa@mit.edu'"
	 <mscoppa@mit.edu>,
        "'schedule@mit.edu'" <schedule@mit.edu>,
        "'scobb@mit.edu'" <scobb@mit.edu>,
        "'shutdowns@mit.edu'"
	 <shutdowns@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Thu, 10 May 2001 12:44:16 -0400
MIME-Version: 1.0
Content-Type: text/plain

> To: 	cbates@mit.edu; E-Zone; graham@mit.edu; gwj@mit.edu; lhill@mit.edu;
> mchin@mit.edu; mdimauro@mit.edu; mscoppa@mit.edu; schedule@mit.edu;
> scobb@mit.edu; shutdowns@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldg. E51 Air Handler 2 Shutdown Request
> 
> 
The following Air Handler 2 shutdown request for Bldg. E51- East Half of
Building on Tuesday, 5/15 is for your review and comment.  Would you please
let me know whehther this does or does not meet with your approval.

Thank you,

Andrea Nichols
Operations Center
8-7872

> Status: Normal
> Building: E51 - East half of Building
> Date: 5/15/2001
> Day: Tuesday
> Time: 6 PM - 10 PM
> System: Air Handler 2
> Duration: 4 hours
> Reason: 
> To free up inlet vanes.
> 
> Effect: 
> Loss of supply ventilation, supply cooling, supply heating and
> exhaust-general air in E51 - East half of the building during the shutdown
> period.
> 
> 