[47766] in Hotline Meeting
E40 - 6/23 - Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Fri Jun 18 13:33:21 1999
Message-Id: <ECFE33C8A3D4D111917900805FBE00008318F4@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'shutdowns@mit.edu'" <shutdowns@MIT.EDU>,
"'lhill@mit.edu'"
<lhill@MIT.EDU>,
"'michaela@mit.edu'" <michaela@MIT.EDU>,
"'mscoppa@mit.edu'" <mscoppa@MIT.EDU>,
"'pmosley@mit.edu'"
<pmosley@MIT.EDU>,
"'foglia@mit.edu'" <foglia@MIT.EDU>, "'achow@mit.edu'" <achow@MIT.EDU>,
"'jfob@mit.edu'" <jfob@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>
Date: Fri, 18 Jun 1999 13:25:59 -0400
Mime-Version: 1.0
Content-Type: text/plain
> To: shutdowns@mit.edu; lhill@mit.edu; michaela@mit.edu; mscoppa@mit.edu;
> pmosley@mit.edu; foglia@mit.edu; achow@mit.edu; jfob@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: E40 - 6/23 - Shutdown Request
>
>
The following shutdown request for Bldg. E40 - all perimeter fan coil units
(air conditioners in perimeter offices) on 6/23 is for your review and
comment. Would you please let me know whether this does or does not meet
with your approval.
Thank you.
Andrea Nichols
Operations Center
8-7872
> Status: Normal
> Building: E40- All perimeter Fan Coil Units
> Date: 6/23/99
> Day: Wednesday
> Time: 8 AM - 11 AM
> System: Air Handler 1 (compressed control air)
> Duration: 3 hours
> Reason:
> To tie-in new filter package to AH1.
>
> Effect:
> Loss of compressed control air (cooling, ventilation and heating) during
> 3-hour shutdown in perimeter offices only.
>
>