[47767] in Hotline Meeting
E18 - 3rd thru 5th floor - 6/22 - Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Fri Jun 18 14:15:21 1999
Message-Id: <ECFE33C8A3D4D111917900805FBE00008318F8@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'shutdowns@mit.edu'" <shutdowns@MIT.EDU>,
"'rmelo@mit.edu'"
<rmelo@MIT.EDU>,
"'aufiero@mit.edu'" <aufiero@MIT.EDU>,
"'jmedeiro@mit.edu'" <jmedeiro@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>
Date: Fri, 18 Jun 1999 14:08:00 -0400
Mime-Version: 1.0
Content-Type: text/plain
> To: shutdowns@mit.edu; rmelo@mit.edu; aufiero@mit.edu; jmedeiro@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: E18 - 3rd thru 5th floor - 6/22 - Shutdown Request
>
>
The following shutdown request for Bldg. E18 - 3rd thru 5th floor on 6/22 is
for your review and comment. Would you please let me know whether this does
or does not have your approval.
Thank you.
Andrea Nichols
Operations Center
8-7872
> Status: Normal
> Building: E18 - 3rd thru 5th floor
> Date: 6/22/99
> Day: Tuesday
> Time: 6 AM - 8 AM
> System: Supply Cooling - AH2 (medium pressure supply air duct)
> Duration: 2 hours
> Reason:
> To remove remaining supply duct from nw construction area.
>
> Effect:
> Loss of supply cooling from Air Handler 2. There will be no air from the
> 3rd through the 5th floors during the shutdown period.
>
>