RE: Canceled for now -Bldg. 2 - 12/29 Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed Dec 23 09:57:29 1998
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'schedule@mit.edu'" <schedule@MIT.EDU>,
"'duggins@math.mit.edu'"
<duggins@math.mit.edu>,
"'capozzi@math.mit.edu'" <capozzi@math.mit.edu>,
"'shutdowns@mit.edu'" <shutdowns@MIT.EDU>,
"'sdimond@mit.edu'"
<sdimond@MIT.EDU>
Cc: Shutdown <Shutdown@PLANT.MIT.EDU>, "'mbj@mit.edu'" <mbj@MIT.EDU>,
Raul Varela <Varela@PLANT.MIT.EDU>, Frank Lewis <flewis@PLANT.MIT.EDU>,
C-Zone <C-Zone@MIT.EDU>
Date: Wed, 23 Dec 1998 09:55:24 -0500
Dear Everyone:
Because of on-going experiments, it has been requested that the above
shutdown request be canceled. I will have further information after the
first of the year concerning a rescheduled date. When I have this
information i will send it along to you.
Thank you.
Andrea Nichols
Operations Center
8-7872
> > Status: Routine
> > Building: 2
> > Date: 12/29/98
> > Day: Tuesday
> > Time: 7:30 AM - 3:30 PM
> > System: All hot and cold water
> > Duration: 8 hours
> > Reason:
> > To remove cross connection
> >
> > Effect:
> > Loss of all water (hot and cold domestic - water for bathrooms,
> > kitchens and drinking fountains) and hot and cold lab process water
> > (water used in labs) during shutdown period.
>
>