Bldg. 2 - 025, 125, 225, 227 and 325 Shutdown Request for 12/30

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu Dec 24 09:44:26 1998

From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'mbj@mit.edu'" <mbj@MIT.EDU>, "'shutdowns@mit.edu'"
	 <shutdowns@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>
Date: Thu, 24 Dec 1998 09:42:24 -0500

> To: 	mbj@mit.edu; shutdowns@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldg. 2 - 025, 125, 225, 227 and 325 Shutdown Request
> for 12/30
> 
> 
The following shutdown request for Bldg. 2 - 025, 125, 225, 227 and 325
on 12/30 is for your review and comment. Would you please let me know
whether or not this has your approval.

Thanks very much and have a happy holiday.

Andrea Nichols
Operations Center
8-7872

> Status: Normal
> Building: 2 - 025, 125, 225, 227 and 325 only
> Date: 12/30/98
> Day: Wednesday
> Time: 7:30 AM - 1:30 PM
> System: Low Pressure Steam
> Duration: 6 hours
> Reason: 
> Adding new valves.
> 
> Effect: 
> Loss of low pressure steam (heat) to the above listed rooms only
> during shutdown period.
> 
> 