Requested Critical Shutdown - All of Bldg. 12 - 12/12/96

daemon@ATHENA.MIT.EDU (OPCTEMP2%MITPPL.bitnet@mitvma.mit.)
Fri Dec 6 11:07:37 1996

Date: Fri, 6 Dec 1996 11:05 EDT
From: OPCTEMP2%MITPPL.bitnet@mitvma.mit.edu
To: schedule@MIT.EDU, edc@MIT.EDU, jenh@MIT.EDU, jcentor@MIT.EDU, ads@MIT.EDU,
        bkaynor@planning.mit.edu, shutdowns@MIT.EDU
X-Envelope-To: ads@mit.edu, edc@mit.edu, jcentor@mit.edu, jenh@mit.edu,
 schedule@mit.edu, shutdowns@mit.edu
X-Vms-To: 
 IN%"schedule@mit.edu, edc@mit.edu, jenh@mit.edu, jcentor@mit.edu, ads@mit.edu,
   bkaynor@planning.mit.edu, shutdowns@mit.edu"

The following requested Critical shutdown for all of Bldg. 12 for 12/12
is for your information and comment. Would you please let me know if
this has your approval or not.

Thanks very much.

Andrea Nichols
Operations Center
8-7872

Building:       All of Building 12, does not affect 12-A
System:         All cold and hot water
Date:           12/12/96
Day:            Thursday
Time:           8:30 AM - 10:30 AM
Duration:       2 hours
Reason:         Leak in 12-056
Effect:         No hot domestic, lab process water, cold domestic
                and lab process water. This means that the restroom
                facilities in Bldg. 12 will not be operational during
                the 2-hour shutdown nor will any of the labs.