[36079] in Hotline Meeting
Re: Requested Critical Shutdown - Bldg. W20 - 12/7/96
daemon@ATHENA.MIT.EDU (Jonathon Weiss)
Thu Dec 5 21:29:46 1996
From: Jonathon Weiss <jweiss@MIT.EDU>
To: mwf@MIT.EDU, shutdowns@MIT.EDU, OPCTEMP2%MITPPL.bitnet@mitvma.mit.edu
Cc: dcns-cluster@MIT.EDU, ops@MIT.EDU, network@MIT.EDU
In-Reply-To: Your message of "Thu, 05 Dec 1996 12:18:55 EST."
<199612051718.MAA22811@tla.MIT.EDU>
Date: Thu, 05 Dec 1996 21:29:35 EST
This shutdown is *not* acceptable. We cannot afford to shutdown the
cooling to the athena cluster until after the end of finals. Before
we can determin whether such a shutdown will be acceptable after
finals, we need to determine what the effects will be on the cooling
of w20-575a (the alarmed room to your left as you enter the Athena
cluster on the 5th floor of w20.) The computers in this room are
servers and may not be shut down. I'm not really responsible for the
cluster, so I can't confirm an exact time with you, but other people
on the shutdowns list can.
Jonathon
> Building: W20 - 5th Floor East & 5th Floor Athena Room
> System: Air Handler 9
> Date: 12/7/96
> Day: Saturday
> Time: 6:00 AM - 2:00 PM
> Duration: 8 hours
> Reason: Repair reheat and preheat coils
> Effect: Loss of supply ventilation, cooling and heating during
> shutdown period.