[171400] in Hotline Meeting
*Extended* Bldg.46-5th Floor Smoke Detector Shutdown Notification
daemon@ATHENA.MIT.EDU (Jessica Westgate)
Thu Aug 8 13:14:57 2013
From: Jessica Westgate <jwestgat@plant.mit.edu>
To: "shutdown-response@mit.edu" <shutdown-response@MIT.EDU>,
"undisclosed_recipients@mit.edu" <undisclosed_recipients@MIT.EDU>,
"graham@mit.edu" <graham@MIT.EDU>, "abm@mit.edu" <abm@MIT.EDU>,
Gerry Desmond
<gdesmond@MIT.EDU>, "handsom@MIT.EDU" <handsom@MIT.EDU>,
"hegarty@mit.edu"
<hegarty@MIT.EDU>,
"rqsmith@mit.edu" <rqsmith@MIT.EDU>,
"bbrown@mit.edu"
<bbrown@MIT.EDU>,
"cgallo34@mit.edu" <cgallo34@MIT.EDU>,
"jstatile@mit.edu"
<jstatile@MIT.EDU>,
"macdonaj@mit.edu" <macdonaj@MIT.EDU>,
"rmarini@mit.edu"
<rmarini@MIT.EDU>,
"mmpatt@mit.edu" <mmpatt@MIT.EDU>,
"OPS RM Campus
Services Main" <rm-mcs@MIT.EDU>,
Ops CSG All <csg-all@MIT.EDU>, "gwolf@mit.edu" <gwolf@MIT.EDU>,
"gillooly@MIT.EDU" <gillooly@MIT.EDU>,
"liberman@mit.edu" <liberman@MIT.EDU>,
"heatherg@mit.edu" <heatherg@MIT.EDU>,
"k_brown@MIT.EDU" <k_brown@MIT.EDU>,
"monaglek@MIT.EDU" <monaglek@MIT.EDU>,
"shutdowns@mit.edu" <shutdowns@MIT.EDU>,
"whomeyer@mit.edu"
<whomeyer@MIT.EDU>,
Ops RM Shutdown <rm-shutdown@MIT.EDU>,
"cp-command@mit.edu" <cp-command@MIT.EDU>,
"safety@mit.edu" <safety@MIT.EDU>, Operators <Operators@plant.mit.edu>,
"DOF Customer Service Center"
<dof-csc@MIT.EDU>,
Ops RM Fire Protection Team <rm-fire-prot-team@MIT.EDU>,
Karen Semerjian <ksemerj@plant.mit.edu>
CC: "jwestgat@mit.edu" <jwestgat@MIT.EDU>, "vang@mit.edu" <vang@MIT.EDU>
Date: Thu, 8 Aug 2013 13:14:49 -0400
Message-ID: <4EEA516695C10541B7CB963FF54A56AF13C687EA68@dof-exchmbx01.facilities.ms.mit.edu>
Content-Language: en-US
Content-Type: text/plain; charset="us-ascii"
MIME-Version: 1.0
Content-Transfer-Encoding: 8bit
The following *Extended* Smoke Detector, shutdown notification for Bldg.46-5th Floor on *Monday, August 12, 2013 through Wednesday, August 14, 2013* from 6:00am-2:00pm is for your information. No response required to this notification. Any question please contact Billy Homeyer 8-0432.
We appreciate your patience while the repairs/renovations are in progress.
Thank you
Jessica Westgate
Operations Center
Type: Normal
Date: August 12, 2013
Day: Monday
Time: 6:00am-2:00pm
Building(s): 46
Room(s): 5th Floor
System: Smoke Detectors
Duration: 8 hours/day
Reason: For soldering, construction dust and all general construction-related activities.
Effect: Loss of smoke detectors in area during the duration of the shutdown.