[170710] in Hotline Meeting

home help back first fref pref prev next nref lref last post

Bldg. 46 - MIBR, 1st Floor MRI Suites, Heating Hot Water Shutdown Request

daemon@ATHENA.MIT.EDU (shutdown-response@MIT.EDU)
Fri Jul 12 11:01:15 2013

From: shutdown-response@MIT.EDU
To: <undisclosed_recipients@MIT.EDU>
Cc: <sudy@MIT.EDU>, <biss@MIT.EDU>
Date: Fri, 12 Jul 2013 11:01:09 -0400
Message-ID: <1B2CB2A39AFB4A4A91112F43F72CBFAC@facilities.ms.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain;
	charset="iso-8859-1"
Content-Transfer-Encoding: 7bit
Content-Class: urn:content-classes:message

The following heating hot water shutdown request for Bldg. 46 - MIBR, 1st Floor MRI Suites, on Thursday, July 18, 2013, 6:00am - 10:00am, is for your information and response.  Any questions, please contact Billy Homeyer, x8-0432.

Please let us know whether this does or does not have your approval.

Thank you,

Jani Findlay
Comprehensive Stewardship Group
Dept. of Facilities
x3-6381

Type: Normal
Date: July 18, 2013
Day: Thursday
Time: 6:00am - 10:00am
Building(s): 46
Room(s): MIBR, 1st Floor MRI Suites
System: Heating Hot Water
Duration: 4 hours
Reason: 
We request a bldg 46-MIBR-1st floor MRI suites eating hot water shutdown, from 6 AM to 10 AM on Thursday, July 18th, 2013 for CTS (Tim Rice 508-962-0188) to tie-in HHW reheats for the 1150 MRI Lab, from the 2nd floor mechanical room 2201, and as part of the 1150 MRI Lab renovation project by Wise Construction (Chris Luongo 781-389-5749). Sudy Nally 8-8010 and Biss Teelucksingh 8-5972 are the MIT project managers.



Effect: 
Loss of heating hot water and supply heating air for the duration of the shutdown.

home help back first fref pref prev next nref lref last post