[170711] in Hotline Meeting
*Modified* Bldg W1-1st floor Smoke Detector Shutdown Notification
daemon@ATHENA.MIT.EDU (Jessica Westgate)
Fri Jul 12 11:13:22 2013
From: Jessica Westgate <jwestgat@plant.mit.edu>
To: "shutdown-response@mit.edu" <shutdown-response@mit.edu>,
"undisclosed_recipients@mit.edu" <undisclosed_recipients@mit.edu>,
"tommyl@mit.edu" <tommyl@mit.edu>, "myersm@MIT.EDU" <myersm@mit.edu>,
"Ops
CSG All" <csg-all@mit.edu>,
OPS RM Campus Services West <rm-wcs@mit.edu>,
"src@MIT.EDU" <src@mit.edu>, "colins@mit.edu" <colins@mit.edu>,
"hmgr@mit.edu" <hmgr@mit.edu>,
"gradhousemasters@mit.edu"
<gradhousemasters@mit.edu>,
"ughousemasters@mit.edu"
<ughousemasters@mit.edu>,
"kcn@mit.edu" <kcn@mit.edu>, "danrod@MIT.EDU"
<danrod@mit.edu>,
"mwhelan@mit.edu" <mwhelan@mit.edu>,
"k_brown@MIT.EDU"
<k_brown@mit.edu>,
"whomeyer@mit.edu" <whomeyer@mit.edu>,
"shutdowns@mit.edu"
<shutdowns@mit.edu>,
Ops RM Shutdown <rm-shutdown@mit.edu>,
"cp-command@mit.edu" <cp-command@mit.edu>,
"safety@mit.edu" <safety@mit.edu>, Operators <Operators@plant.mit.edu>,
DOF Customer Service Center
<dof-csc@mit.edu>,
Ops RM Fire Protection Team <rm-fire-prot-team@mit.edu>
CC: "jwestgat@mit.edu" <jwestgat@mit.edu>,
"whomeyer@mit.edu"
<whomeyer@mit.edu>
Date: Fri, 12 Jul 2013 11:13:11 -0400
Message-ID: <4EEA516695C10541B7CB963FF54A56AF13C5842F2A@dof-exchmbx01.facilities.ms.mit.edu>
Content-Language: en-US
Content-Type: text/plain; charset="us-ascii"
MIME-Version: 1.0
Content-Transfer-Encoding: 8bit
The following *Modified* Fire protection shutdown notification for Bldg W1, 1st floor on Monday, July 1, 2013 through Thursday, August 15, 2013 (regular work days only, excluding *Sat 7/13 from 9:00am-5:00pm*) from 6:00AM-3:00PM, is for your information. No response is required to this notification. Any questions, please contact Billy Homeyer 8-0432.
We appreciate your patience while the repairs/renovations are in progress.
Thank You
Jessica Westgate
Operations Center
Type: Normal
Date: July 1, 2013
Day: Monday
Time: 6:00AM-3:00PM
Building(s): W1
Room(s): 1st floor
System: Fire protection Smoke detectors
Duration: 9 hours/day
Reason: to replace the floor in the dining area
Effect: Loss of smoke detectors in the area during the duration of the shutdown.