[170149] in Hotline Meeting
Approved - Bldg. 7-All - Emergency Power, Emergency Egress
daemon@ATHENA.MIT.EDU (Jennifer Garland)
Thu Jun 13 13:19:51 2013
From: Jennifer Garland <jennygar@plant.mit.edu>
To: Jim Harrington <lordjim@MIT.EDU>, "laugh@mit.edu" <laugh@MIT.EDU>,
"tommyl@mit.edu" <tommyl@MIT.EDU>, "myersm@MIT.EDU" <myersm@MIT.EDU>,
"skendall@mit.edu" <skendall@MIT.EDU>,
OPS RM Campus Services Main
<rm-mcs@MIT.EDU>,
Ops Custodial Admin & Support Staff <cust-staff@MIT.EDU>,
"gearin@mit.edu" <gearin@MIT.EDU>,
"segaloff@MIT.EDU" <segaloff@MIT.EDU>, "jcoen@mit.edu" <jcoen@MIT.EDU>,
"gayle@mit.edu" <gayle@MIT.EDU>, "Michael
Smith" <masmith@MIT.EDU>,
"sbghosh@MIT.EDU" <sbghosh@MIT.EDU>, "fenner@mit.edu" <fenner@MIT.EDU>,
"annm@mit.edu" <annm@MIT.EDU>, "mberg@mit.edu" <mberg@MIT.EDU>,
"jbnorman@mit.edu" <jbnorman@MIT.EDU>,
"bridburg@MIT.EDU" <bridburg@MIT.EDU>, "whc@mit.edu" <whc@MIT.EDU>,
"hillery@mit.edu" <hillery@MIT.EDU>,
"kyegian@MIT.EDU" <kyegian@MIT.EDU>,
"shutdowns@mit.edu" <shutdowns@MIT.EDU>,
"whomeyer@mit.edu"
<whomeyer@MIT.EDU>,
"ksemerj@mit.edu" <ksemerj@MIT.EDU>,
"wradochi@mit.edu"
<wradochi@MIT.EDU>,
"sgilliga@mit.edu" <sgilliga@MIT.EDU>,
Ops RM Shutdown
<rm-shutdown@MIT.EDU>, DOF EHS <dof-ehs@MIT.EDU>,
"cp-command@mit.edu"
<cp-command@MIT.EDU>,
"safety@mit.edu" <safety@MIT.EDU>,
Operators
<Operators@plant.mit.edu>,
DOF Customer Service Center <dof-csc@MIT.EDU>,
"Ops Custodial Admin & Support Staff" <cust-staff@MIT.EDU>
CC: "jennygar@mit.edu" <jennygar@MIT.EDU>, "biss@mit.edu" <biss@MIT.EDU>
Date: Thu, 13 Jun 2013 13:19:41 -0400
Message-ID: <4EEA516695C10541B7CB963FF54A56AF13C3A83834@dof-exchmbx01.facilities.ms.mit.edu>
Content-Language: en-US
Content-Type: text/plain; charset="us-ascii"
MIME-Version: 1.0
Content-Transfer-Encoding: 8bit
The following Approved Emergency Power, Emergency Egress Lighting, Heat Tape, Tel/data Power Panel Shutdown is for bldg. 7 - All on Friday, June 14, 2013 from 12:01AM til 5:00AM is for your information. Any questions please contact Billy Homeyer x8-0432.
Thank you,
Jennifer M. Garland
Repair and Maintenance
4-4350
Type: Normal
Date: June 14, 2013
Day: Friday
Time: 12:01AM - 5:00AM
Building(s): 7
Room(s): All
System: emergency power,telephones,lighting,corridor/stairs,
Duration: 12:01AM - 5:00AM
Reason:
We request a bldg 7 normal emergency power shutdown bldg 7-108E emergency power panel - affecting the bldg 7 tel/data power panel and bldg 7-all emergency egress lighting - from 12:01 AM to 5 AM on Friday morning, June 14th, 2013 for MacNichol Electric (Mike Bryson 781-760-7416) tying-in power for the 7-304 fire alarm transponder and investigating the bldg 7 power panel 'B' as part of the 7-304 Architecture Offices project by Renovations Inc (Jim Abbisso 617-594-7650). Biss Teelucksingh 2-5972 is the MIT project manager.
Effect:
Loss of emergency power,telephones,lighting,corridor/stairs for the duration of this shutdown.