[169986] in Hotline Meeting

home help back first fref pref prev next nref lref last post

Bldg. 6-All Labs (fume hoods) Normal 480V Bldg Power Shutdown, Bldg. 2-017E (reheat, lab waste) Power Panel MDP (Chemistry project)

daemon@ATHENA.MIT.EDU (shutdown-response@MIT.EDU)
Thu Jun 6 12:52:39 2013

From: shutdown-response@MIT.EDU
To: <undisclosed_recipients@MIT.EDU>
Cc: <jennygar@MIT.EDU>, <mdeluga@MIT.EDU>
Date: Thu, 6 Jun 2013 12:52:28 -0400
Message-ID: <677BFE586ED843FD841905340A0E36C0@facilities.ms.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain;
	charset="iso-8859-1"
Content-Transfer-Encoding: 7bit
Content-Class: urn:content-classes:message

The following Normal 480V Bldg Power Shutdown is for bldg. 6-All labs (fume hoods) and  Power Panel MDP (Chemistry project) is for bldg. 2-017E (reheat, lab waste) Shutdown on Thursday, June 20, 2013 from 6:00PM til Friday, June 21, 2013 6:00AM is for your information and approval.  Any questions please contact Billy Homeyer x8-0432.


Would you please let us know if this does or does not have your approval.

Thank you,


Jennifer M. Garland
Repair and Maintenance
4-4350

Type: Normal
Date: June 20, 2013
Day: Thursday
Time: 6:00PM (Thu) - 6:00AM (Fri)
Building(s): 6-All labs and bldg. 2 - 017E
Room(s): labs (fume hoods)bldg. 6 - reheat, lab waste for bldg. 2
System: building power,heating hot water, supply heating, laboratory, lab waste, exhaust hood
Duration: 6:00PM (Thu) - 6:00AM (Fri)
Reason: 
We request a bldg 2-217E 480V distribution panel MDP normal bldg power shutdown from 6 PM on Thursday evening, June 20th to 6 AM on Friday morning, June 21st, 2013 for Bennett Electric (John Shaw 617-293-4806) to install a 225A circuit breaker for future new rooftop air handling units and to refeed the 2-PH power panel MP4PH1 (conduit relocation) as part of the 2 Chemistry renovation project by Bond Brothers (Jesse Conklin 617-938-4175). Marty Deluga 4-5081 and Joe Collins 3-3621 are the MIT project managers.

Panel MDP feeds the 2 penthouse panel MP4PH1 which in turn feeds EF1A, 1B, 1C and 1D (bldg 6 lab fume hood exhaust fans shutdowns requested on another shutdown request for the same time frame), some roof lighting and a Schneider CX panel.
MDP also feeds 2-012 power panel MP422 which in turn feeds the heating hot water system (reheats), the bldg 2 lab waste transfer system and a local mechanical room exhaust fan.   



Effect: 
Loss building power,heating hot water, supply heating, laboratory, lab waste, exhaust hood for the duration of this shutdown. 