Bldg. 18 - 3rd and 4th Floors, Process Chilled Water Shutdown Request
daemon@ATHENA.MIT.EDU (shutdown-response@MIT.EDU)
Thu Jun 6 09:53:52 2013
From: shutdown-response@MIT.EDU
To: <undisclosed_recipients@MIT.EDU>
Cc: <ajsilva@MIT.EDU>, <mgodding@MIT.EDU>
Date: Thu, 6 Jun 2013 09:53:47 -0400
Message-ID: <47B32A7027FD4E2CA6348C0CA4A78ADC@facilities.ms.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain;
charset="iso-8859-1"
Content-Transfer-Encoding: 7bit
Content-Class: urn:content-classes:message
The following process chilled water shutdown request for Bldg. 18 - 3rd and 4th Floors, on Wednesday, June 12, 2013, 7:00am - 12:00pm (for the 4th Floor) and Thursday, June 13, 2013, 7:00am - 12:00pm (for the 3rd Floor), is for your information and approval. Any questions, please contact Joe Silva, x3-1602.
Please let us know whether this does or does not have your approval.
Thank you,
Jani Findlay
Comprehensive Stewardship Group
Dept. of Facilities
x3-6381
Type: Normal
Date: June 12, 2013
Day: Wednesday
Time: 7:00am - 12:00pm each day
Building(s): 18
Room(s): 3rd and 4th Floors
System: Process Chilled Water
Duration: 5 hours/day
Reason:
installation of shut off valves for the maintenance of the strainers for hoods
Effect:
Loss of process chilled water for the duration of the shutdown each day.