[169226] in Hotline Meeting

home help back first fref pref prev next nref lref last post

Bldg. 35-029 - Building Power Shutdown

daemon@ATHENA.MIT.EDU (Jennifer Garland)
Mon May 13 13:50:56 2013

From: Jennifer Garland <jennygar@plant.mit.edu>
To: "oconaill@mit.edu" <oconaill@mit.edu>, "DICKP@MIT.EDU" <DICKP@mit.edu>,
        "alz@MIT.EDU" <alz@mit.edu>,
        OPS RM Campus Services Main <rm-mcs@mit.edu>,
        "lmcgon@mit.edu" <lmcgon@mit.edu>, "icuevas@mit.edu" <icuevas@mit.edu>,
        "ktanaka@mit.edu" <ktanaka@mit.edu>,
        "culpepper@mit.edu" <culpepper@mit.edu>,
        "davidrod@mit.edu" <davidrod@mit.edu>,
        "sbghosh@MIT.EDU" <sbghosh@mit.edu>, "maxine@mit.edu" <maxine@mit.edu>,
        "bpant@mit.edu" <bpant@mit.edu>,
        "MIT
 Schedules Office" <schedules@mit.edu>,
        "shutdowns@mit.edu"
	<shutdowns@mit.edu>,
        Gary Saffie <gsaffie@plant.mit.edu>,
        Ops RM Shutdown
	<rm-shutdown@mit.edu>, DOF EHS <dof-ehs@mit.edu>,
        "cp-command@mit.edu"
	<cp-command@mit.edu>,
        "safety@mit.edu" <safety@mit.edu>,
        Operators
	<Operators@plant.mit.edu>,
        DOF Customer Service Center <dof-csc@mit.edu>,
        "Ops Custodial Admin & Support Staff" <cust-staff@mit.edu>
CC: "jennygar@mit.edu" <jennygar@mit.edu>,
        Steven Gilligan
	<sgilliga@plant.mit.edu>
Date: Mon, 13 May 2013 13:50:46 -0400
Message-ID: <4EEA516695C10541B7CB963FF54A56AF13AD41F6CB@dof-exchmbx01.facilities.ms.mit.edu>
Content-Language: en-US
Content-Type: text/plain; charset="us-ascii"
MIME-Version: 1.0
Content-Transfer-Encoding: 8bit

The following Approved Building Power Shutdown is for bldg. 35-029 - basement area on Tuesday, May 14, 2013 from 5:00am - 7:00am is for your information.  Any questions please contact Steve Gilligan 253-8079.



Thank you,


Jennifer M. Garland
Repair and Maintenance
4-4350

Type: Normal
Date: May 14, 2013
Day: Tuesday
Time: 5:00am - 7:00am
Building(s): 35
Room(s): basement, rm. 029 and surrounding labs.
System: access controls, building power, computers, corridor/stairs lights
Duration: 5:00am - 7:00am
Reason: 
This is to change over circuit breaker from 30 amp to a 20 amp.

Effect: 
Loss of access controls, building power, computers, corridor/stairs lights for the duration of this shutdown. 