Bldg. 7-019 and surrounding area -Building Power Shutdown
daemon@ATHENA.MIT.EDU (shutdown-response@MIT.EDU)
Mon May 13 12:54:40 2013
From: shutdown-response@MIT.EDU
To: <undisclosed_recipients@MIT.EDU>
Cc: <jennygar@MIT.EDU>, <sgilliga@plant.mit.edu>
Date: Mon, 13 May 2013 12:54:33 -0400
Message-ID: <312A7C75981B45A3ACD6E74812BEE3D7@facilities.ms.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain;
charset="iso-8859-1"
Content-Transfer-Encoding: 7bit
Content-Class: urn:content-classes:message
The following Building Power Shutdown is for bldg. 7-019 and surrounding area on Friday, May 17, 2013 from 5:00am - 7:00am is for your information and approval. Any questions please contact Steve Gilligan x3-8079.
Would you please let us know if this does or does not have your approval.
Thank you,
Jennifer M. Garland
Repair and Maintenance
4-4350
Type: Normal
Date: May 17, 2013
Day: Friday
Time: 5:00am - 7:00am
Building(s): 7
Room(s): 019 - surrounding area
System: access controls, building power, computers
Duration: 5:00am - 7:00am
Reason:
This is to wire new electrical circuit in area.
Effect:
Loss of building power for the duration of this shutdown.