[160578] in Hotline Meeting
Bldg. 66 - Floors 1 through 5, West - Air Handler 2 Shutdown Request
daemon@ATHENA.MIT.EDU (shutdown-response@MIT.EDU)
Mon Jul 30 14:04:49 2012
From: shutdown-response@MIT.EDU
To: <undisclosed_recipients@MIT.EDU>
Cc: <billvit@MIT.EDU>
Date: Mon, 30 Jul 2012 14:04:47 -0400
Message-ID: <7E5CB6F1EF484716A92870F8824DBE4F@facilities.ms.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain;
charset="iso-8859-1"
Content-Transfer-Encoding: 7bit
Content-Class: urn:content-classes:message
The following air handler 2 shutdown request for Bldg. 66 - Floors 1 through 5, West, on Friday, August 3, 2012, 6:00am - 8:00am and Friday, August 24, 2012, at 5:00pm through 6:00am on Monday, August 27, 2012, is for your information and response. Any questions, please contact Billy Homeyer, x8-0432.
Please let us know whether this does or does not have your approval.
Thank you,
Jani Findlay
Repair and Maintenance
x3-6381
Type: Normal
Date: August 3, 2012
Day: Friday
Time: 6:00am - 8:00am (8/3); 5:00pm (8/24) - 6:00am (8/27)
Building(s): 66
Room(s): Floors 1 through 5 West
System: Air Handler 2 Induction
Duration: 2 hours/61 hours
Reason:
We request bldg 66-AH2 shutdowns from 6 AM to 8 AM on Friday, August 3rdand from 5 PM on Friday evening August 24th to 6 AM on Monday morning, August 27th for Ducts Inc. (Darren King 617-908 7370) to measure and subsequently replace two subbasement fire dampers allowing time for the duct sealant to cure and as part of the bldg 66-steam leak recovery project by Shawmut Construction (Doug Tower 617-622-7731). Bill
Vitkosky 3-6517 is the MIT project manager.
Bldg 66-west side offices on floors 1 thru 5 will be affected.
Effect:
Loss of supply cooling air for the duration of the shutdown.