[160579] in Hotline Meeting
Bldg. 10 - All, Natural Gas and Domestic Hot and Cold Water Shutdown Request
daemon@ATHENA.MIT.EDU (shutdown-response@MIT.EDU)
Mon Jul 30 14:10:37 2012
From: shutdown-response@MIT.EDU
To: <undisclosed_recipients@MIT.EDU>
Cc: <jcombs@MIT.EDU>
Date: Mon, 30 Jul 2012 14:10:32 -0400
Message-ID: <947B344AE1D14FFF891611970CA7F7EF@facilities.ms.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain;
charset="iso-8859-1"
Content-Transfer-Encoding: 7bit
Content-Class: urn:content-classes:message
The following natural gas and domestic hot and cold water shutdown request for Bldg. 10 - All, on Friday, August 3, 2012, 5:00am - 7:30am, is for your information and response. Any questions, please contact Billy Homeyer, x8-0432.
Please let us know whether this does or does not have your approval.
Thank you,
Jani Findlay
Repair and Maintenance
x3-6381
Type: Normal
Date: August 3, 2012
Day: Friday
Time: 5:00am - 7:30am
Building(s): 10
Room(s): All
System: Natural Gas and Domestic Hot and Cold Water
Duration: 2.5 hours
Reason:
We request bldg 10-all natural gas and domestic water shutdown from 5 AM to 7:30 AM on Friday, August 3rd to tie-in the new stove and dw to tie-in the new sink as part of the 10-320 kitchen renovation/exhaust system upgrade project by Shawmut Construction (Paul McGee 61-839-0412/Dick O'Connell 617-839-6186). Jennifer Combs 3-7671 is the MIT project manager.
Effect:
Loss of domestic hot and cold water and natural gas for the duration of the shutdown.