Bldg. 14 - All, Air Handlers 1 through 5 Shutdown Notification
daemon@ATHENA.MIT.EDU (shutdown-response@MIT.EDU)
Mon Jul 30 13:52:40 2012
From: shutdown-response@MIT.EDU
To: <undisclosed_recipients@MIT.EDU>
Cc: <jmannion@MIT.EDU>
Date: Mon, 30 Jul 2012 13:52:32 -0400
Message-ID: <81E57B7DBECC496F897D7A00816AA1AB@facilities.ms.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain;
charset="iso-8859-1"
Content-Transfer-Encoding: 7bit
Content-Class: urn:content-classes:message
The following air handlers 1 through 5 shutdown notification for Bldg. 14 - All, on Wednesday, August 1, 2012, 7:00am - 8:00am, is for your information. Any questions, please contact Jack Mannion, x8-5468.
We apologize for any inconvenience this may cause you.
Thank you,
Jani Findlay
Repair and Maintenance
x3-6381
Type: Normal
Date: August 1, 2012
Day: Wednesday
Time: 7:00am - 8:00am
Building(s): 14
Room(s): All
System: Air Handlers 1 through 5
Duration: 1 hour
Reason:
replacement of power panel breakers (AH3/RF3 and AH4/RF4)
Effect:
There will be no loss of any air since the units are off on the noraml time schedule during the time this work will be taking place.