Bldg. 13-All, Fan Supply AH1 #701700 shutdown request

daemon@ATHENA.MIT.EDU (shutdown-response@MIT.EDU)
Wed May 9 10:26:17 2012

From: shutdown-response@MIT.EDU
To: <undisclosed_recipients@MIT.EDU>
Cc: <shutdowns@MIT.EDU>, <whomeyer@MIT.EDU>, <gsaffie@plant.mit.edu>,
        <alegere@plant.mit.edu>
Date: Wed, 9 May 2012 10:26:14 -0400
Message-ID: <CD3818EA042449198654696BA44D9729@facilities.ms.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain;
	charset="iso-8859-1"
Content-Transfer-Encoding: 7bit
Content-Class: urn:content-classes:message

The following Fan Supply AH1 #701700 shutdown request for Bldg. 13 - All from Saturday, May 12, 2012 to Sunday, May 13, 2012 is for your information and response. Any questions please contact Billy Homeyer x8-0432.

Would you please let us know whether this does or does not have your approval.

Thank you,
Bernadette Drinkwater
Repair and Maintenance
x3-0938

We request a Bldg 13-AH1 shutdown from 6 AM on Saturday, May 12th to 9 AM on Sunday, May 13th, 2012 for United Sheet Metal (Fred O'Connor 781-871-1066) to install three reheat coils and associated supply air ductwork in 13-3064 and to allow time for duct sealant to properly cure as part of the NSF funded 13-3064 lab renovation project by Barr and Barr Builders (John Bidgood 508-686-0870). Biss Teelucksingh 2-5972 is the MIT project manager.

Type: Normal
Date: May 12, 2012
Day: Saturday
Time: 6:00am (Sat) - 9:00am (Sun)
Building(s): 13
Room(s): All
System: AH1 #701700
Duration: 27 hours
Reason: 
Tie-in reheat coil supply air ductwork and seal it in the lab 13-3064.

Effect: 
Loss of ventilation.

This message was sent the following recipients: rm-mcs@mit.edu; cust-staff@mit.edu; jbartels@MIT.EDU; mbulsara@mit.edu; jeileef@mit.edu; elk@MIT.EDU; schedules@mit.edu; jingkong@mit.edu; 