Bldg. 13-All, Fan Supply AH1 #701700 shutdown request
daemon@ATHENA.MIT.EDU (shutdown-response@MIT.EDU)
Wed May 9 10:26:16 2012
From: shutdown-response@MIT.EDU
To: <undisclosed_recipients@MIT.EDU>
Cc: <shutdowns@MIT.EDU>, <whomeyer@MIT.EDU>, <gsaffie@plant.mit.edu>,
<alegere@plant.mit.edu>
Date: Wed, 9 May 2012 10:26:12 -0400
Message-ID: <FF23B1014AAB4B2C9F657C5E5037179B@facilities.ms.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain;
charset="iso-8859-1"
Content-Transfer-Encoding: 7bit
Content-Class: urn:content-classes:message
The following Fan Supply AH1 #701700 shutdown request for Bldg. 13 - All from Saturday, May 12, 2012 to Sunday, May 13, 2012 is for your information and response. Any questions please contact Billy Homeyer x8-0432.
Would you please let us know whether this does or does not have your approval.
Thank you,
Bernadette Drinkwater
Repair and Maintenance
x3-0938
We request a Bldg 13-AH1 shutdown from 6 AM on Saturday, May 12th to 9 AM on Sunday, May 13th, 2012 for United Sheet Metal (Fred O'Connor 781-871-1066) to install three reheat coils and associated supply air ductwork in 13-3064 and to allow time for duct sealant to properly cure as part of the NSF funded 13-3064 lab renovation project by Barr and Barr Builders (John Bidgood 508-686-0870). Biss Teelucksingh 2-5972 is the MIT project manager.
Type: Normal
Date: May 12, 2012
Day: Saturday
Time: 6:00am (Sat) - 9:00am (Sun)
Building(s): 13
Room(s): All
System: AH1 #701700
Duration: 27 hours
Reason:
Tie-in reheat coil supply air ductwork and seal it in the lab 13-3064.
Effect:
Loss of ventilation.