[694] in I/T Delivery

home help back first fref pref prev next nref lref last post

5ESS Uprade and Replacement Project

daemon@ATHENA.MIT.EDU (Lu Keohane)
Fri Feb 8 18:23:15 2002

Message-Id: <5.0.2.1.2.20020208181907.00a4bce0@hesiod>
Date: Fri, 08 Feb 2002 18:23:05 -0500
To: delivery@mit.edu
From: Lu Keohane <lu@MIT.EDU>
Mime-Version: 1.0
Content-Type: multipart/alternative;
	boundary="=====================_25287993==_.ALT"

--=====================_25287993==_.ALT
Content-Type: text/plain; charset="iso-8859-1"; format=flowed
Content-Transfer-Encoding: quoted-printable


Project Notebook


Project Name:           5ESS Upgrade and Replacement
Project Leader:         Louise T. Keohane
Report Date:            February 7, 2002
URL:                    http://web.mit.edu/is/delivery/5ess/



Accomplishments in the Month of January:
=B7       Programmed the of 3A Translator and will begin to test on-line=
 with=20
the Voice Mail system.
=B7       Relocated all ACD links on the MDF
=B7       ACD Hardware identified and will be ordered.
=B7       ACD Software and RTU (right to use) fees being negotiated with=20
Lucent/Avaya and IEX Corp.
=B7       Plans to install and test new ACD hardware & software have begun.
=B7       Resolved SM1 issues associated with the modem pool lines.
=B7       Continue to Build and make modifications to the database for the=
=20
new ICE9 program that simulates the    new 5ESS.
=B7       Have performed some testing of the ICE 9 database and will=
 continue=20
after code modifications are        complete.
=B7       Testing of analog and ISDN services is as follows:
         o       E19     70% of analog & 31% of ISDN
         o       24      80% of analog & 11 % of ISDN
         o       NW12    96% of analog & 59 % of ISDN
         o       Total Analog lines tested:       9,522
         o       Total ISDN lines tested:         9,944
=B7       Verify testing plan from all 3 locations including IVR, ACD,=
 VMail,=20
Modem pool, etc.
=B7       Continued to host meetings with the Lucent=92s management team to=
=20
investigate options on an interim basis         to providing additional=20
ISDN/analog services from NW12 and Bldg. 24 until the new cutover date=20
(e.g. at         least a few months).  Both of these two options that=20
Lucent provided were not sufficient, as they did not       meet MIT=92s=20
requirements.
=B7       5EOps suggested a third option, to place EXM 6 in the hallway of=
=20
Bldg. 24.  After working with Facilities       on a preliminary walk=20
through of space needed and available in the existing corridor, we=20
presented this         option to Lucent.  Lucent is very resistant to=20
performing this work before cutover.
o        FYI:  Lucent, due to space constraints within the building 24=20
switch room, designed EXM 6 to be placed after the removal of the old 5ESS=
=20
classic equipment.  The expected time line for installing EXM6 after=20
cutover is a minimum 30 days (again, after the old equipment is=20
removed).  Had the cutover taken place on Martin Luther King weekend, MIT=20
would have had plenty of time to remove the classic equipment out, install=
=20
EXM 6 and load balance both EXM 5 & 6 to provide the appropriate dial tone=
=20
to meet customer demand and project schedules. Setting up a new cutover=20
date, MIT,  would have taken into consideration the additional 30 days for=
=20
EXM 6 to come on-line.
=B7       Lucent had many reasons why they could not perform option three=
 and=20
the 5E Ops team had as many reasons why they could and should:
1.      Lucent would require a minimum of $400k with a maximum of $500K to=
=20
perform this work.  (EXM 6 has always been part of the original proposal,=20
so MIT has already contracted to pay Lucent to install this equipment in=20
Bldg. 24 as part of the overall project).
o       When trying to get Lucent to identify the equipment that MIT would=
=20
require now for approximately $400-500K, they agreed to provide a=20
printout.  None of the 5ESS Project team to date, has seen any=
 documentation.
2.      Lucent=92s sales team suggested that the room wouldn't be ready soon=
=20
enough and it would move the cutover date out  to 30 days.  Accepting the=20
additional 30 days, and suggesting the room could be built within a week=20
(thanks to Joe Collins in Facility), Lucent turned back to needing the=20
additional monies ($400-500K) to perform the extra work.
=B7       An example of what would the scenario look like if we performed=
 the=20
cutover in April:     I/S announces the new cutover date (e.g. April 15th=20
), to the community.  Yet, we also tell the community that not only are we=
=20
cutting over, but as of April 15th and until at least June 1st, we can not=
=20
provide any additional ISDN or analog services from the Bldg. 24=20
switchroom.  (Doesn't seem like a viable plan to me since Lucent has been=20
unable to commit to all goals mutually agreed upon since the start of this=
=20
project.  Also, it=92s very possible that the 30 days they are suggesting it=
=20
will take is more realistically like > 45 days).  Also, MIT chose not to=20
cutover on MLK weekend, because Lucent had less than 40% of all analog=20
lines accurately configured and wired on the new switch.  They hadn't even=
=20
begun the verification process for the ISDN lines and given that the analog=
=20
failed at such a high rate, we consider we were looking at a higher rate of=
=20
failure on the ISDN lines.  Estimated to be around:  10% accurate.  (Need I=
=20
say more)?
3.      Lucent then presented to MIT that we would have a contamination=20
issue and we would need to sign a waiver that relieved Lucent for ANY=20
failing equipment from the 24 switchroom.  First, let me say, since being=20
in I/S we have done many projects that required construction.  Some, walls=
=20
were added, removed or changed as well as reinforcing the floors of NW12=20
and E19.  None of these projects ever contaminated the =93 5ESS equipment=94=
 or=20
jeopardized its integrity. Second, the plan we discussed with Facilities=20
for the expansion of the switchroom,  would have been completed by:
o       A) Placing plastic up against the back door;  B) Building an=20
extension off of the wall of the switchroom; C) Removing the door, the door=
=20
jam;  and D) Begin installing EXM 6 and lastly after the classic is=20
removed, the new equipment is rolled into its permanent space and the room=
=20
is returned to its original configuration.   Lucent never visited MIT or=20
asked any questions to get a thorough understanding of the whole=20
plan.  Typically Lucent will make a site visit and perform a walk through=20
with MIT.

4.      5ESS Ops team was then told that it would require money to perform=
=20
new engineering schematics and that it would put EXM 6 at risk at cutover=20
after the old equipment is removed.  The risk, they describe, is that a=20
=93hot=94 slide would be required to align the equipment and this could lead=
 to=20
many problems (e.g. equipment failures, outages, breaks, etc.).  5ESS Ops=20
reminded them that the entire switch is being performed as a =93hot=94=
 slide.

5.      Since money seemed to be a driving force for Lucent not to perform=
=20
option three, the 5ESS Ops team explored with possibility with Lucent to=20
receive their second payment (to be received at cutover) in hopes that we=20
can move this project forward and ease whatever financial stress was=20
blocking the completion of this project.  Lucent never responded to this=20
suggestion.  And as a side note:  Lucent has already invested an additional=
=20
4-6 million since starting this project.  (This does not affect MIT=92s=20
bottom line on the purchasing price of the new switch).

6.      Lucent then suggested that they haven't done anything to pursue=20
option three because they have been waiting three weeks for the floor plans=
=20
for Bldg. 24=92s switchroom.  This is interesting because, 1) 5E Ops=20
suggested Option three only two weeks ago and 2) they are the one=92s that=
=20
gave us the first set of floor plans to work from because it has the=20
equipment line ups.

7.      They also told us that we would be passing up a try and buy program=
=20
that was made available with option two.  The equipment would provide the=20
5ESS with Sonet capabilities.  This isn't a technological improvement that=
=20
we have been investigating and find it to be more important for the teams=20
to focus on the existing project of bringing the new switch on-line before=
=20
adding equipment we are not sure the community wants or would ever=20
use.  This in no way would provide an interim solution to the ISDN requests=
=20
5ESS Support is being asked to provide.

8.      In a nutshell, we will continue forward with the installation of=20
the new 5ESS switch.  The team will continue to discuss and  hopefully=20
influence the installation of EXM 6.  The team will continue to work across=
=20
teams and with our customers to fulfill every requirement.

Goals for the month of February and until cutover:

We will:
=B7       Continue testing all analog lines and tracing and repairing=
 troubles.
=B7       Continue testing all ISDN lines and correcting problems as they=
 occur.
=B7       Continue to influence the installation of EXM 6 to occur in=20
parallel with the cutover.
=B7       Continue with database comparisons; the classic 5ESS to ICE9, the=
=20
new 5ESS to the classic 5ESS and      the new ICE9 database to the existing=
=20
ICE9 database) must be 100% accurate.  Making modifications as    necessary.
=B7       Complete all jumpers to the MDF=92s
=B7       To begin spot checking of all jumpers with attention paid to all=
=20
moves, adds & changes that have occurred       since December.
=B7       Continue tracking all MAC=92s (Moves, Adds & Changes) since August=
 to=20
insure all jumpers have moved       with the relocation/changes that=20
occurred on telephones.
=B7       Perform voice-overs for all the recorded announcements in the new=
=20
switch (this includes the ACD         recorded announcements).
=B7       Continue testing the integration of 5ESS with the existing voice=
=20
mail, IVR & ACD systems with the new   5ESS and making modifications as=20
necessary.
=B7       Perform 300 + frame verification and ISDN card changes.
=B7       Communicate to community via article, web notification, email, and=
=20
presentations around the 5ESS        upgrade and replacement and possible=20
dates for cutover.
=B7       Continue testing all widgets (e.g. modem pool, circuits, etc.)=20
twice and repair when necessary.
=B7       Test all boards for the new SM6 on SM1, 2 and 3.  (SM6=92s=
 equipment=20
was temporarily taken and placed     in SM1, 2 and 4 when problems=
 occurred).
=B7       Install New ACD hardware and software.  Cutover old system to new=
=20
platform.  Will coordinate with I/S=92s         help desk.
=B7       Test ACD integration before and after upgrade.
=B7       Complete spreadsheets to database conversion and debug
=B7       Prepare for cutover
=B7       Night of cutover change 250 ISDN U-A to U-B cards from 24 and=
 NW12.



Challenges:
=B7       Lucent

=B7       The installation and testing teams were working around the clock=
=20
with 52 technicians.  Recently, they are only working 8 hours a day with 25=
=20
technicians.  Lucent has suggested that they could present to the 5E team a=
=20
date on February 1st that they would be confident to commit to a new=20
cutover date.

         Inspirational quote:  "Make one person happy each day, and in=20
forty years
         you will have made 14,600 human beings happy for a
         little time, at least."


Thanks,
Lu

=BA=BF=BA
  ~=20
--=====================_25287993==_.ALT
Content-Type: text/html; charset="iso-8859-1"
Content-Transfer-Encoding: quoted-printable

<html>
<div align=3D"center">
<font size=3D5>Project Notebook<br>
<br>
<br>
</font></div>
<font face=3D"Arial Narrow, Helvetica">Project
Name:<x-tab>&nbsp;&nbsp;&nbsp;</x-tab><x-tab>&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&=
nbsp;&nbsp;&nbsp;</x-tab>5ESS
Upgrade and Replacement<br>
Project
Leader:<x-tab>&nbsp;</x-tab><x-tab>&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp=
;&nbsp;</x-tab>Louise
T. Keohane<br>
Report
Date:<x-tab>&nbsp;&nbsp;&nbsp;&nbsp;</x-tab><x-tab>&nbsp;&nbsp;&nbsp;&nbsp;&=
nbsp;&nbsp;&nbsp;&nbsp;</x-tab>February
7, 2002<br>
URL:<x-tab>&nbsp;&nbsp;&nbsp;&nbsp;</x-tab><x-tab>&nbsp;&nbsp;&nbsp;&nbsp;&n=
bsp;&nbsp;&nbsp;&nbsp;</x-tab><x-tab>&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nb=
sp;&nbsp;</x-tab></font><a href=3D"http://web.mit.edu/is/delivery/5ess/"=
 eudora=3D"autourl"><font face=3D"Arial Narrow, Helvetica"=
 color=3D"#0000FF"><b><u>http://web.mit.edu/is/delivery/5ess/<br>
<br>
<br>
<br>
</a></font><font face=3D"Arial Narrow, Helvetica">Accomplishments in the
Month of January:<br>
</u></b></font><font face=3D"Symbol"=
 size=3D4>=B7<x-tab>&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;</x-tab></font=
><font face=3D"Arial Narrow, Helvetica">Programmed
the of 3A Translator and will begin to test on-line with the Voice Mail
system.<br>
</font><font face=3D"Symbol"=
 size=3D4>=B7<x-tab>&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;</x-tab></font=
><font face=3D"Arial Narrow, Helvetica">Relocated
all ACD links on the MDF<br>
</font><font face=3D"Symbol"=
 size=3D4>=B7<x-tab>&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;</x-tab></font=
><font face=3D"Arial Narrow, Helvetica">ACD
Hardware identified and will be ordered.<br>
</font><font face=3D"Symbol"=
 size=3D4>=B7<x-tab>&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;</x-tab></font=
><font face=3D"Arial Narrow, Helvetica">ACD
Software and RTU (right to use) fees being negotiated with Lucent/Avaya
and IEX Corp.<br>
</font><font face=3D"Symbol"=
 size=3D4>=B7<x-tab>&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;</x-tab></font=
><font face=3D"Arial Narrow, Helvetica">Plans
to install and test new ACD hardware &amp; software have begun.&nbsp;
<br>
</font><font face=3D"Symbol"=
 size=3D4>=B7<x-tab>&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;</x-tab></font=
><font face=3D"Arial Narrow, Helvetica">Resolved
SM1 issues associated with the modem pool lines.<br>
</font><font face=3D"Symbol"=
 size=3D4>=B7<x-tab>&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;</x-tab></font=
><font face=3D"Arial Narrow, Helvetica">Continue
to Build and make modifications to the database for the new ICE9 program
that simulates the <x-tab>&nbsp;&nbsp;&nbsp;</x-tab>new 5ESS.<br>
</font><font face=3D"Symbol"=
 size=3D4>=B7<x-tab>&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;</x-tab></font=
><font face=3D"Arial Narrow, Helvetica">Have
performed some testing of the ICE 9 database and will continue after code
modifications are
<x-tab>&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;</x-tab>complete.<br>
</font><font face=3D"Symbol"=
 size=3D4>=B7<x-tab>&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;</x-tab></font=
><font face=3D"Arial Narrow, Helvetica">Testing
of analog and ISDN services is as follows:<br>
</font><font face=3D"Courier New, Courier"=
 size=3D4><x-tab>&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;</x-tab>o<x=
-tab>&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;</x-tab></font><font=
 face=3D"Arial Narrow, Helvetica">E19<x-tab>&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;</=
x-tab>70%
of analog &amp; 31% of
ISDN<x-tab>&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;</x-tab><br>
</font><font face=3D"Courier New, Courier"=
 size=3D4><x-tab>&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;</x-tab>o<x=
-tab>&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;</x-tab></font><font=
 face=3D"Arial Narrow, Helvetica">24<x-tab>&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nb=
sp;</x-tab>80%
of analog &amp; 11 % of ISDN<br>
</font><font face=3D"Courier New, Courier"=
 size=3D4><x-tab>&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;</x-tab>o<x=
-tab>&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;</x-tab></font><font=
 face=3D"Arial Narrow, Helvetica">NW12<x-tab>&nbsp;&nbsp;&nbsp;&nbsp;</x-tab=
>96%
of analog &amp; 59 % of ISDN<br>
</font><font face=3D"Courier New, Courier"=
 size=3D4><x-tab>&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;</x-tab>o<x=
-tab>&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;</x-tab></font><font=
 face=3D"Arial Narrow, Helvetica">Total
Analog lines tested:<x-tab>&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;</x-tab>
9,522<br>
</font><font face=3D"Courier New, Courier"=
 size=3D4><x-tab>&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;</x-tab>o<x=
-tab>&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;</x-tab></font><font=
 face=3D"Arial Narrow, Helvetica">Total
ISDN lines
tested:<x-tab>&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;</x-tab>
9,944&nbsp; <br>
</font><font face=3D"Symbol"=
 size=3D4>=B7<x-tab>&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;</x-tab></font=
><font face=3D"Arial Narrow, Helvetica">Verify
testing plan from all 3 locations including IVR, ACD, VMail, Modem pool,
etc.<br>
</font><font face=3D"Symbol"=
 size=3D4>=B7<x-tab>&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;</x-tab></font=
><font face=3D"Arial Narrow, Helvetica">Continued
to host meetings with the Lucent=92s management team to investigate options
on an interim basis
<x-tab>&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;</x-tab>to
providing additional ISDN/analog services from NW12 and Bldg. 24 until
the new cutover date (e.g. at
<x-tab>&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;</x-tab>least a
few months).&nbsp; Both of these two options that Lucent provided were
not sufficient, as they did not
<x-tab>&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;</x-tab>meet MIT=92s
requirements.<br>
</font><font face=3D"Symbol"=
 size=3D4>=B7<x-tab>&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;</x-tab></font=
><font face=3D"Arial Narrow, Helvetica">5EOps
suggested a third option, to place EXM 6 in the hallway of Bldg.
24.&nbsp; After working with Facilities
<x-tab>&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;</x-tab>on a preliminary walk
through of space needed and available in the existing corridor, we
presented this
<x-tab>&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;</x-tab>option to
Lucent.&nbsp; Lucent is very resistant to performing this work before
cutover. </font>
<dl>
<dl><font face=3D"Courier New, Courier" size=3D4>
<dd>o<x-tab>&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;</x-tab></font><font=
 face=3D"Arial Narrow, Helvetica">
FYI:&nbsp; Lucent, due to space constraints within the building 24 switch=
 room, designed EXM 6 to be placed after the removal of the old 5ESS classic=
 equipment.&nbsp; The expected time line for installing EXM6 after cutover=
 is a minimum 30 days (again, after the old equipment is removed).&nbsp; Had=
 the cutover taken place on Martin Luther King weekend, MIT would have had=
 plenty of time to remove the classic equipment out, install EXM 6 and load=
 balance both EXM 5 &amp; 6 to provide the appropriate dial tone to meet=
 customer demand and project schedules. Setting up a new cutover date,=
 MIT,&nbsp; would have taken into consideration the additional 30 days for=
 EXM 6 to come on-line.</font>
</dl><font face=3D"Symbol" size=3D4>
<dd>=B7<x-tab>&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;</x-tab></font><font=
 face=3D"Arial Narrow, Helvetica">Lucent had many reasons why they could not=
 perform option three and the 5E Ops team had as many reasons why they could=
 and should:</font><font face=3D"Arial Narrow, Helvetica" size=3D4>
<dd>1.<x-tab>&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;</x-tab></font><font=
 face=3D"Arial Narrow, Helvetica">Lucent would require a minimum of $400k=
 with a maximum of $500K to perform this work.&nbsp; (EXM 6 has always been=
 part of the original proposal, so MIT has already contracted to pay Lucent=
 to install this equipment in Bldg. 24 as part of the overall=
 project).</font>
<dl><font face=3D"Courier New, Courier" size=3D4>
<dd>o<x-tab>&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;</x-tab></font><font=
 face=3D"Arial Narrow, Helvetica">When trying to get Lucent to identify the=
 equipment that MIT would require now for approximately $400-500K, they=
 agreed to provide a printout.&nbsp; None of the 5ESS Project team to date,=
 has seen any documentation.</font>
</dl><font face=3D"Arial Narrow, Helvetica" size=3D4>
<dd>2.<x-tab>&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;</x-tab></font><font=
 face=3D"Arial Narrow, Helvetica">Lucent=92s sales team suggested that the=
 room wouldn't be ready soon enough and it would move the cutover date=
 out&nbsp; to 30 days.&nbsp; Accepting the additional 30 days, and=
 suggesting the room could be built within a week (thanks to Joe Collins in=
 Facility), Lucent turned back to needing the additional monies ($400-500K)=
 to perform the extra work.&nbsp; </font>
<dl><font face=3D"Symbol">
<dd>=B7<x-tab>&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;</x-tab></font><font=
 face=3D"Arial Narrow, Helvetica">An example of what would the scenario look=
 like if we performed the cutover in April:&nbsp;&nbsp;&nbsp;&nbsp; I/S=
 announces the new cutover date (e.g. April 15</font><font face=3D"Arial=
 Narrow, Helvetica" size=3D1><sup>th</sup></font><font face=3D"Arial Narrow,=
 Helvetica"> ), to the community.&nbsp; Yet, we also tell the community that=
 not only are we cutting over, but as of April 15</font><font face=3D"Arial=
 Narrow, Helvetica" size=3D1><sup>th</sup></font><font face=3D"Arial Narrow,=
 Helvetica"> and until at least June 1</font><font face=3D"Arial Narrow,=
 Helvetica" size=3D1><sup>st</sup></font><font face=3D"Arial Narrow,=
 Helvetica">, we can not provide any additional ISDN or analog services from=
 the Bldg. 24 switchroom.&nbsp; (Doesn't seem like a viable plan to me since=
 Lucent has been unable to commit to all goals mutually agreed upon since=
 the start of this project.&nbsp; Also, it=92s very possible that the 30=
 days they are suggesting it will take is more realistically like &gt; 45=
 days).&nbsp; Also, MIT chose not to cutover on MLK weekend, because Lucent=
 had less than 40% of all analog lines accurately configured and wired on=
 the new switch.&nbsp; They hadn't even begun the verification process for=
 the ISDN lines and given that the analog failed at such a high rate, we=
 consider we were looking at a higher rate of failure on the ISDN=
 lines.&nbsp; Estimated to be around:&nbsp; 10% accurate.&nbsp; (Need I say=
 more)?&nbsp; </font>
</dl><font face=3D"Arial Narrow, Helvetica" size=3D4>
<dd>3.<x-tab>&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;</x-tab></font><font=
 face=3D"Arial Narrow, Helvetica">Lucent then presented to MIT that we would=
 have a contamination issue and we would need to sign a waiver that relieved=
 Lucent for ANY failing equipment from the 24 switchroom.&nbsp; First, let=
 me say, since being in I/S we have done many projects that required=
 construction.&nbsp; Some, walls were added, removed or changed as well as=
 reinforcing the floors of NW12 and E19.&nbsp; None of these projects ever=
 contaminated the =93 5ESS equipment=94 or jeopardized its integrity.=
 Second, the plan we discussed with Facilities for the expansion of the=
 switchroom,&nbsp; would have been completed by:&nbsp; </font>
<dl>
<dl>
<dl>
<dl>
<dl><font face=3D"Courier New, Courier">
<dd>o<x-tab>&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;</x-tab></font><font=
 face=3D"Arial Narrow, Helvetica">A) Placing plastic up against the back=
 door;&nbsp; B) Building an extension off of the wall of the switchroom; C)=
 Removing the door, the door jam;&nbsp; and D) Begin installing EXM 6 and=
 lastly after the classic is removed, the new equipment is rolled into its=
 permanent space and the room is returned to its original=
 configuration.&nbsp;&nbsp; Lucent never visited MIT or asked any questions=
 to get a thorough understanding of the whole plan.&nbsp; Typically Lucent=
 will make a site visit and perform a walk through with MIT.<br>
<br>
</font>
</dl>
</dl>
</dl>
</dl>
</dl><font face=3D"Arial Narrow, Helvetica" size=3D4>
<dd>4.<x-tab>&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;</x-tab></font><font=
 face=3D"Arial Narrow, Helvetica">5ESS Ops team was then told that it would=
 require money to perform new engineering schematics and that it would put=
 EXM 6 at risk at cutover after the old equipment is removed.&nbsp; The=
 risk, they describe, is that a =93hot=94 slide would be required to align=
 the equipment and this could lead to many problems (e.g. equipment=
 failures, outages, breaks, etc.).&nbsp; 5ESS Ops reminded them that the=
 entire switch is being performed as a =93hot=94 slide.
</dl>&nbsp;&nbsp; </font>
<dl><font face=3D"Arial Narrow, Helvetica" size=3D4>
<dd>5.<x-tab>&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;</x-tab></font><font=
 face=3D"Arial Narrow, Helvetica">Since money seemed to be a driving force=
 for Lucent not to perform option three, the 5ESS Ops team explored with=
 possibility with Lucent to receive their second payment (to be received at=
 cutover) in hopes that we can move this project forward and ease whatever=
 financial stress was blocking the completion of this project.&nbsp; Lucent=
 never responded to this suggestion.&nbsp; And as a side note:&nbsp; Lucent=
 has already invested an additional 4-6 million since starting this=
 project.&nbsp; (This does not affect MIT=92s bottom line on the purchasing=
 price of the new switch).<br>
<br>
</font><font face=3D"Arial Narrow, Helvetica" size=3D4>
<dd>6.<x-tab>&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;</x-tab></font><font=
 face=3D"Arial Narrow, Helvetica">Lucent then suggested that they haven't=
 done anything to pursue option three because they have been waiting three=
 weeks for the floor plans for Bldg. 24=92s switchroom.&nbsp; This is=
 interesting because, 1) 5E Ops suggested Option three only two weeks ago=
 and 2) they are the one=92s that gave us the first set of floor plans to=
 work from because it has the equipment line ups.<br>
<br>
</font><font face=3D"Arial Narrow, Helvetica" size=3D4>
<dd>7.<x-tab>&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;</x-tab></font><font=
 face=3D"Arial Narrow, Helvetica">They also told us that we would be passing=
 up a try and buy program that was made available with option two.&nbsp; The=
 equipment would provide the 5ESS with Sonet capabilities.&nbsp; This isn't=
 a technological improvement that we have been investigating and find it to=
 be more important for the teams to focus on the existing project of=
 bringing the new switch on-line before adding equipment we are not sure the=
 community wants or would ever use.&nbsp; This in no way would provide an=
 interim solution to the ISDN requests 5ESS Support is being asked to=
 provide.<br>
<br>
</font><font face=3D"Arial Narrow, Helvetica" size=3D4>
<dd>8.<x-tab>&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;</x-tab></font><font=
 face=3D"Arial Narrow, Helvetica">In a nutshell, we will continue forward=
 with the installation of the new 5ESS switch.&nbsp; The team will continue=
 to discuss and&nbsp; hopefully influence the installation of EXM 6.&nbsp;=
 The team will continue to work across teams and with our customers to=
 fulfill every requirement.<br>
<br>

</dl><b><u>Goals for the month of February and until cutover:<br>
<br>
</u></b>We will: <br>
</font><font face=3D"Symbol"=
 size=3D4>=B7<x-tab>&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;</x-tab></font=
><font face=3D"Arial Narrow, Helvetica">Continue testing all analog lines=
 and tracing and repairing troubles.<br>
</font><font face=3D"Symbol"=
 size=3D4>=B7<x-tab>&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;</x-tab></font=
><font face=3D"Arial Narrow, Helvetica">Continue testing all ISDN lines and=
 correcting problems as they occur.<br>
</font><font face=3D"Symbol"=
 size=3D4>=B7<x-tab>&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;</x-tab></font=
><font face=3D"Arial Narrow, Helvetica">Continue to influence the=
 installation of EXM 6 to occur in parallel with the cutover.<br>
</font><font face=3D"Symbol"=
 size=3D4>=B7<x-tab>&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;</x-tab></font=
><font face=3D"Arial Narrow, Helvetica">Continue with database comparisons;=
 the classic 5ESS to ICE9, the new 5ESS to the classic 5ESS and=
 <x-tab>&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;</x-tab>the new ICE9 database to the=
 existing ICE9 database) must be 100% accurate.&nbsp; Making modifications=
 as <x-tab>&nbsp;&nbsp;&nbsp;</x-tab>necessary.<br>
</font><font face=3D"Symbol"=
 size=3D4>=B7<x-tab>&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;</x-tab></font=
><font face=3D"Arial Narrow, Helvetica">Complete all jumpers to the=
 MDF=92s<br>
</font><font face=3D"Symbol"=
 size=3D4>=B7<x-tab>&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;</x-tab></font=
><font face=3D"Arial Narrow, Helvetica">To begin spot checking of all=
 jumpers with attention paid to all moves, adds &amp; changes that have=
 occurred <x-tab>&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;</x-tab>since=
 December.<br>
</font><font face=3D"Symbol"=
 size=3D4>=B7<x-tab>&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;</x-tab></font=
><font face=3D"Arial Narrow, Helvetica">Continue tracking all MAC=92s=
 (Moves, Adds &amp; Changes) since August to insure all jumpers have moved=
 <x-tab>&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;</x-tab>with the=
 relocation/changes that occurred on telephones.<br>
</font><font face=3D"Symbol"=
 size=3D4>=B7<x-tab>&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;</x-tab></font=
><font face=3D"Arial Narrow, Helvetica">Perform voice-overs for all the=
 recorded announcements in the new switch (this includes the ACD=
 <x-tab>&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;</x-tab>recorded=
 announcements).<br>
</font><font face=3D"Symbol"=
 size=3D4>=B7<x-tab>&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;</x-tab></font=
><font face=3D"Arial Narrow, Helvetica">Continue testing the integration of=
 5ESS with the existing voice mail, IVR &amp; ACD systems with the new=
 <x-tab>&nbsp;&nbsp;</x-tab>5ESS and making modifications as necessary.<br>
</font><font face=3D"Symbol"=
 size=3D4>=B7<x-tab>&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;</x-tab></font=
><font face=3D"Arial Narrow, Helvetica">Perform 300 + frame verification and=
 ISDN card changes.<br>
</font><font face=3D"Symbol"=
 size=3D4>=B7<x-tab>&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;</x-tab></font=
><font face=3D"Arial Narrow, Helvetica">Communicate to community via=
 article, web notification, email, and presentations around the 5ESS=
 <x-tab>&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;</x-tab>upgrade and=
 replacement and possible dates for cutover.<br>
</font><font face=3D"Symbol"=
 size=3D4>=B7<x-tab>&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;</x-tab></font=
><font face=3D"Arial Narrow, Helvetica">Continue testing all widgets (e.g.=
 modem pool, circuits, etc.) twice and repair when necessary.<br>
</font><font face=3D"Symbol"=
 size=3D4>=B7<x-tab>&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;</x-tab></font=
><font face=3D"Arial Narrow, Helvetica">Test all boards for the new SM6 on=
 SM1, 2 and 3.&nbsp; (SM6=92s equipment was temporarily taken and placed=
 <x-tab>&nbsp;&nbsp;&nbsp;&nbsp;</x-tab>in SM1, 2 and 4 when problems=
 occurred).<br>
</font><font face=3D"Symbol"=
 size=3D4>=B7<x-tab>&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;</x-tab></font=
><font face=3D"Arial Narrow, Helvetica">Install New ACD hardware and=
 software.&nbsp; Cutover old system to new platform.&nbsp; Will coordinate=
 with I/S=92s=
 <x-tab>&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;</x-tab>help=
 desk.<br>
</font><font face=3D"Symbol"=
 size=3D4>=B7<x-tab>&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;</x-tab></font=
><font face=3D"Arial Narrow, Helvetica">Test ACD integration before and=
 after upgrade.<br>
</font><font face=3D"Symbol"=
 size=3D4>=B7<x-tab>&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;</x-tab></font=
><font face=3D"Arial Narrow, Helvetica">Complete spreadsheets to database=
 conversion and debug<br>
</font><font face=3D"Symbol"=
 size=3D4>=B7<x-tab>&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;</x-tab></font=
><font face=3D"Arial Narrow, Helvetica">Prepare for cutover<br>
</font><font face=3D"Symbol"=
 size=3D4>=B7<x-tab>&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;</x-tab></font=
><font face=3D"Arial Narrow, Helvetica">Night of cutover change 250 ISDN U-A=
 to U-B cards from 24 and NW12.<br>
<br>
<br>
<br>
<b><u>Challenges:</u></b></font>
<dl>
<dl><font face=3D"Symbol" size=3D4>
<dd>=B7<x-tab>&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;</x-tab></font><font=
 face=3D"Arial Narrow, Helvetica">Lucent<br>
<br>
</font><font face=3D"Symbol" size=3D4>
<dd>=B7<x-tab>&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;</x-tab></font><font=
 face=3D"Arial Narrow, Helvetica">The installation and testing teams were=
 working around the clock with 52 technicians.&nbsp; Recently, they are only=
 working 8 hours a day with 25 technicians.&nbsp; Lucent has suggested that=
 they could present to the 5E team a date on February 1</font><font=
 face=3D"Arial Narrow, Helvetica" size=3D1><sup>st</sup></font><font=
 face=3D"Arial Narrow, Helvetica"> that they would be confident to commit to=
 a new cutover date.&nbsp; <br>
<br>

</dl>
</dl><x-tab>&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;</x-tab>Inspirat=
ional quote:&nbsp; </font>&quot;Make one person happy each day, and in forty=
 years<br>
<x-tab>&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;</x-tab>you will have=
 made 14,600 human beings happy for a<br>
<x-tab>&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;&nbsp;</x-tab>little time,=
 at least.&quot;<br>
<br>
<br>

<font color=3D"#0000FF">Thanks,<br>
Lu<br>
<br>
=BA</font><font color=3D"#800080">=BF</font><font color=3D"#0000FF">=BA</fon=
t> <br>
<font color=3D"#FF0000">&nbsp;~</font> </html>

--=====================_25287993==_.ALT--


home help back first fref pref prev next nref lref last post