[582] in I/T Delivery

home help back first fref pref prev next nref lref last post

5ESS Upgrade & Replacement

daemon@ATHENA.MIT.EDU (Lu Keohane)
Thu Oct 4 13:38:19 2001

Message-Id: <5.0.2.1.2.20011004133418.00a00100@hesiod>
Date: Thu, 04 Oct 2001 13:38:07 -0400
To: delivery@mit.edu, njj@mit.edu
From: Lu Keohane <lukeohan@MIT.EDU>
Cc: telecom-ops@mit.edu
Mime-Version: 1.0
Content-Type: multipart/alternative;
	boundary="=====================_16534249==_.ALT"

--=====================_16534249==_.ALT
Content-Type: text/plain; charset="us-ascii"; format=flowed

Project Name: 5ESS upgrade & replacement
Project Leader: Lu Keohane
Report Date: October 3, 2001
Submitted by: Lu Keohane
URL: http://web.mit.edu/is/delivery/5ess

This Month's Accomplishments:
SMF installed between switch sites
Negotiated additional equipment/work completed (costing $36K) to be 
provided at NO CHARGE
Negotiated additional AMIS terminals (costing approx. $16K) to be provided 
at NO CHARGE
Frame verification ongoing (NW12 nearly completed; 24 1/2 completed; E19 
started)
New verification methods designed by 5E Ops Team identified to speed process
AM & CM3 installed and powered in E19
Additional A/C provided with creatively using the A/C from the modem pool
SM's and power cabinet installations ongoing
Conduits to roof for GPS Antennae installed
Testing of GPS signaling completed
Installation of GPS Antennae from 5E's to roofs completed
Priority telephone numbers/circuit lists being compiled
U-A to U-B card conversions in E19 ongoing (approximately 350 of 600 
completed)
ICE9 database upgrade/reconciliation/updates ongoing
Preparing for adjunct equipment (e.g. voicemail, ACD, IVR, modem pool, etc) 
conversion to new switch
Preparing to align support team for night of cutover
New blocks mounted onto frame in NW12
New code written in ICE 9 to handle architectural changes in the 5ESS-2000 
and MDF's stenciled to match ICE 9 database.
Cable and Pair changes modified daily to match frame verification process
ICE 9 updated to reflect clean-up and reconciliation of work results 
verification process



Next Month's Plans:
Finish Frame verification
Continue ICE9 database upgrade/reconciliation/updates
Install MDF blocks in 24 and E19
Install "S" clips for dual block work
Testing of analog in NW12 (board to board)
Install AMIS terminals in all switchrooms
Modifications made to voice mail
Continue U-A to U-B card conversions in E19
Plan for U-A to U-B card conversions in 24 and NW12
Continue compiling priority telephone numbers/circuit lists
Continue SM and power installations
Begin testing Bldg 24 analog
Begin integration between old classic switch database and new SM2K switch 
database
Continue preparation for adjunct systems (e.g. voicemail ACD, IVR, modem 
pool, etc) conversion to new switch
Turn on additional cabinets, (Miscellaneous bays, LTP, SM's, AIU's)







Issues:
Retirement package at Lucent taken by majority of our Lucent Team
Account
Layoffs affecting 1/3 of the installation team
Lost some Lucent installation staff at MIT to assist installation of 3 new 
5ESS in New York at  "Ground Zero"
Closely monitoring Air Conditioning in all three switch sites (especially E19)
Switch rooms becoming increasingly crowded with people/equipment, making 
ongoing daily Telephone moves/adds/changes difficult to complete in normal 
time frames (due to overlapping on the MDF and at the terminals)
5ESS Operations core team and additional resource team members working on 
the project are becoming increasingly stressed trying to maintain day to 
day service on the current switch at the level to which our customer base 
has become accustomed, while installing the new 5ESS (a full time project 
all by itself), and dealing with daily technical/administrative issues and 
problems related to loss of MIT administrative staff/support
Continue to be instrumental in all areas of Telecom in the day-to-day stuff 
and while also working multiple projects and/or tasks.
Key 5ESS Ops personnel are being tapped into for other emerging issues on 
campus.
Double workload for the team is resulting in 60+ hour work-weeks with 
limited time off
etc.

Team Dynamics:
The 5ESS core team and additional resources being utilized come from a 
strong foundation and work well together; consequently, morale is OK right 
now, although the increasing stress level is taking it's toll.  The 
strength of this team is held together by not only the pride they have in 
the importance of the work they do but also out of respect and admiration 
for their coworkers.

Key Learnings:
Expect the unexpected (7x24)
Make vendors feel responsible and push them to do better
Strategies move with the project
Develop a creative solution to deal with the unexpected on the fly.
People need recognition, respect and time-off








--=====================_16534249==_.ALT
Content-Type: text/html; charset="us-ascii"

<html>
Project Name: 5ESS upgrade &amp; replacement<br>
Project Leader: Lu Keohane<br>
Report Date: October 3, 2001<br>
Submitted by: Lu Keohane<br>
URL:
<a href="http://web.mit.edu/is/delivery/5ess" eudora="autourl">http://web.mit.edu/is/delivery/5ess</a><br>
<br>
This Month's Accomplishments:<br>

<dl>
<dd>SMF installed between switch sites 
<dd>Negotiated additional equipment/work completed (costing $36K) to be
provided at NO CHARGE 
<dd>Negotiated additional AMIS terminals (costing approx. $16K) to be
provided at NO CHARGE
<dd>Frame verification ongoing (NW12 nearly completed; 24 1/2 completed;
E19 started) 
<dd>New verification methods designed by 5E Ops Team identified to speed
process 
<dd>AM &amp; CM3 installed and powered in E19
<dd>Additional A/C provided with creatively using the A/C from the modem
pool 
<dd>SM's and power cabinet installations ongoing 
<dd>Conduits to roof for GPS Antennae installed 
<dd>Testing of GPS signaling completed
<dd>Installation of GPS Antennae from 5E’s to roofs completed
<dd>Priority telephone numbers/circuit lists being compiled 
<dd>U-A to U-B card conversions in E19 ongoing (approximately 350 of 600
completed)
<dd>ICE9 database upgrade/reconciliation/updates ongoing 
<dd>Preparing for adjunct equipment (e.g. voicemail, ACD, IVR, modem
pool, etc) conversion to new switch 
<dd>Preparing to align support team for night of cutover
<dd>New blocks mounted onto frame in NW12 
<dd>New code written in ICE 9 to handle architectural changes in the
5ESS-2000 and MDF’s stenciled to match ICE 9 database.
<dd>Cable and Pair changes modified daily to match frame verification
process 
<dd>ICE 9 updated to reflect clean-up and reconciliation of work results
verification process <br>
<br>
<br>
<br>

</dl>Next Month's Plans:<br>

<dl>
<dd>Finish Frame verification 
<dd>Continue ICE9 database upgrade/reconciliation/updates 
<dd>Install MDF blocks in 24 and E19
<dd>Install “S” clips for dual block work
<dd>Testing of analog in NW12 (board to board)
<dd>Install AMIS terminals in all switchrooms
<dd>Modifications made to voice mail
<dd>Continue U-A to U-B card conversions in E19 
<dd>Plan for U-A to U-B card conversions in 24 and NW12 
<dd>Continue compiling priority telephone numbers/circuit lists 
<dd>Continue SM and power installations 
<dd>Begin testing Bldg 24 analog
<dd>Begin integration between old classic switch database and new SM2K
switch database 
<dd>Continue preparation for adjunct systems (e.g. voicemail ACD, IVR,
modem pool, etc) conversion to new switch 
<dd>Turn on additional cabinets, (Miscellaneous bays, LTP, SM’s,
AIU’s)<br>
<br>
<br>
<br>
<br>
<br>
<br>
<br>

</dl>Issues:<br>

<dl>
<dd>Retirement package at Lucent taken by majority of our Lucent Team
<dd>Account
</dl>Layoffs affecting 1/3 of the installation team
<dl>
<dd>Lost some Lucent installation staff at MIT to assist installation of
3 new 5ESS in New York at&nbsp; &quot;Ground Zero&quot; 
<dd>Closely monitoring Air Conditioning in all three switch sites
(especially E19)
<dd>Switch rooms becoming increasingly crowded with people/equipment,
making ongoing daily Telephone moves/adds/changes difficult to complete
in normal time frames (due to overlapping on the MDF and at the
terminals)
<dd>5ESS Operations core team and additional resource team members
working on the project are becoming increasingly stressed trying to
maintain day to day service on the current switch at the level to which
our customer base has become accustomed, while installing the new 5ESS (a
full time project all by itself), and dealing with daily
technical/administrative issues and problems related to loss of MIT
administrative staff/support 
<dd>Continue to be instrumental in all areas of Telecom in the day-to-day
stuff and while also working multiple projects and/or tasks.
<dd>Key 5ESS Ops personnel are being tapped into for other emerging
issues on campus.
<dd>Double workload for the team is resulting in 60+ hour work-weeks with
limited time off 
<dd>etc. <br>
<br>

</dl>Team Dynamics: <br>

<dl>
<dd>The 5ESS core team and additional resources being utilized come from
a strong foundation and work well together; consequently, morale is OK
right now, although the increasing stress level is taking it's
toll.&nbsp; The strength of this team is held together by not only the
pride they have in the importance of the work they do but also out of
respect and admiration for their coworkers.&nbsp; <br>
<br>

</dl>Key Learnings: <br>

<dl>
<dd>Expect the unexpected (7x24)
<dd>Make vendors feel responsible and push them to do better
<dd>Strategies move with the project
<dd>Develop a creative solution to deal with the unexpected on the fly. 
<dd>People need recognition, respect and time-off<br>
<br>
<br>
<br>
<br>
<br>
<br>
<br>

</dl></html>