HR-Payroll project monthly update

daemon@ATHENA.MIT.EDU (dan fitzgerald)
Thu Mar 1 09:08:05 2001

Message-Id: <200103011408.JAA04047@melbourne-city-street.MIT.EDU>
Date: Thu, 01 Mar 2001 09:08:01 -0500
To: delivery@mit.edu
From: dan fitzgerald <danfitz@MIT.EDU>
Mime-Version: 1.0
Content-Type: multipart/alternative;
	types="text/plain,text/html";
	boundary="=====================_1187571667==_.ALT"

--=====================_1187571667==_.ALT
Content-Type: text/plain; charset="us-ascii"

Project Name: HR-Payroll Project
Project Leader: Dan Fitzgerald
Report Date: March 1, 2001  
URL: http://web.mit.edu/is/delivery/hrpayroll/

General 
----------
- Benefits module is 1st rollout of HR, planned for summer of 2001. Project
team continues to stay on schedule. Significant milestone in Feb included a QA
report by SAP senior consultant. The report was very positive but did include
some deficits around documentation and a section of the requirements
definition. Steps are underway to improve both areas. The development team
also
met a key milestone in Feb, completion of baseline configuration.

Accomplishments in February
-----------------------------------------
- Recruiting design team, focusing especially on applicant tracking component,
completed the current process map and conducted 2 demos.
- Employment verification process team in progress. Completed map of current
process.
- Organization management process team assembled and 1st meeting called.
- Interactive Voice Response vendors evaluated. Focus is on now on 1 vendor,
Talx.

Goals for March
-------------------------
- IVR vendor selected and workplan drafted.
- Improve financial controls around project budget.
- Benefits change management and training plan approved.
- Real data used for conversion testing in SAP development environment.

Issues 
--------
- Version 4.6C of SAP requires Workplace to run ESS. Workarounds to support 3
benefits transactions for this summer are being worked.

Additional comments 
--------------------------
- Receiving terrific support from IS department on many fronts. 
--=====================_1187571667==_.ALT
Content-Type: text/html; charset="us-ascii"

<html>
Project Name: HR-Payroll Project<br>
Project Leader: Dan Fitzgerald<br>
Report Date: March 1, 2001&nbsp; <br>
URL:
<a href="http://web.mit.edu/is/delivery/hrpayroll/" eudora="autourl"><font color="#0000FF"><u>http://web.mit.edu/is/delivery/hrpayroll/</a><br>
<br>
</font></u><font color="#000000">General <br>
----------<br>
- Benefits module is 1st rollout of HR, planned for summer of 2001.
Project team continues to stay on schedule. Significant milestone in Feb
included a QA report by SAP senior consultant. The report was very
positive but did include some deficits around documentation and a section
of the requirements definition. Steps are underway to improve both areas.
The development team also met a key milestone in Feb, completion of
baseline configuration.<br>
<br>
Accomplishments in February<br>
-----------------------------------------<br>
- Recruiting design team, focusing especially on applicant tracking
component, completed the current process map and conducted 2 demos.<br>
- Employment verification process team in progress. Completed map of
current process.<br>
- Organization management process team assembled and 1st meeting
called.<br>
- Interactive Voice Response vendors evaluated. Focus is on now on 1
vendor, Talx.<br>
<br>
Goals for March<br>
-------------------------<br>
- IVR vendor selected and workplan drafted.<br>
- Improve financial controls around project budget.<br>
- Benefits change management and training plan approved.<br>
- Real data used for conversion testing in SAP development
environment.<br>
<br>
Issues <br>
--------<br>
- Version 4.6C of SAP requires Workplace to run ESS. Workarounds to
support 3 benefits transactions for this summer are being worked.<br>
<br>
Additional comments <br>
--------------------------<br>
- Receiving terrific support from IS department on many
fronts.</font></html>