Project name: Internet Transaction Server (ITS) 
Project leader: Mark Damian 
Report date: January 2, 2000 
Submitted by: Mark Damian
url: web.mit.edu/its-alive

Accomplishments past period: 
- Preparing ITS Pilot transactions for SAP 4.6C Endorsement Test the
      week of 1/15.
- Attended an ITS meeting sponsored by Jim Bruce and Chuck Shaw to
     discuss risk assessment of the existing ITS architecture.
- Met with IS/R3-Admin and IS/ASST to discuss roles and responsibilities
     of ongoing ITS maintenance and support.
- Began evaluating new SAP4.6C tool, the Web Application Builder

Goals for the coming period
- Follow up to make sure that all those who had action items from the
     12/18 meeting deliver as scheduled.
- Complete the evaluation of the Web Application Builder

Issues
-  The SNC error is still being researched by our MIT Kerberos experts.
        With this solved, we can move from pilot to general rollout.
-  Resources continue to be an issue.  Too many are spread too thin.
-  I have not seen the ITS Linux version which should have been delivered
     by the end of '00.

Team Dynamics
Things are OK.

Closing
This was to be our last delivery report.  Depending on the progress of
outstanding items, I may continue to send updates.



Sincerely,

Mark Damian
MIT Financial Systems Services
Sr. Business Systems Analyst