Project Name: IS Work
The project formerly known as "IS Operational Plan Alive!"
Project Leaders: Tim McGovern
Report Date: October 2, 2000
Project Notebook: http://web.mit.edu/is/delivery/iswork/
System is available for review at http://mit.edu/is/work/
Accomplishments past period (September)
- Continued to execute against plan set in August
- ITLT froze Strategic Plan content and IS Work db took that content
- Project DB frozen and IS Work db took that content
- Updatable IS Work DB announced for ITLT review & updates
- Continuing to debug final system
Goals for the coming period (October)
- Stabilize design of system
- Coordinate final demise of Project DB
- Ensure IS Web Pages links to Project DB now point to new system
- Migrate IS Work to a production quality facility
- Announce widespead availability of the system
- Begin to manage IS work on the basis of the database's contents.
Issues
- No new ones at this time.
Key learnings
- When given the time, and opportunity, we _can_ pull together and make something
good happen.
Team dynamics
- Working well. Some issues remain with how to better use expert consultants
in
a project that's centered around a small core team.
Additional comments
- None