On Aug 20, 2012, at 16:25 , Leo Bicknell <bicknell@ufp.org> wrote:
> In a message written on Mon, Aug 20, 2012 at 04:12:22PM -0400, Patrick =
W. Gilmore wrote:

>> The story: A piece of underground cable went bad.  The techs didn't =
pull new underground cable.  They decided it was better to do it "arial" =
(if you can call 2 feet "arial").  They took apart the two pedestals on =
either side of the break and ran a new strand of RG6 (yes, the same =
stuff you use inside your home, not the outside-plant rated stuff) tied =
to trees with rope.
>=20
> Why is that cable still in place?
>=20
> That's a hint, not really a question. :)

Because VZ LTE, while nice in general, is not good enough for Jezzibell =
to use all day for a week. :)

--=20