[70067] in Hotline Meeting
Bldg. E19 - Hot/Cold Domestic/Lab Process Water Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Tue Nov 25 13:00:45 2003
Message-ID: <568F0AEE7A57D511923900508B55645103D71DA1@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'cschultz@mit.edu'" <cschultz@mit.edu>,
"'dlking@mit.edu'"
<dlking@mit.edu>,
"'donnab@MIT.EDU'" <donnab@mit.edu>,
"'dreid@mit.edu'"
<dreid@mit.edu>, "'dshea@mit.edu'" <dshea@mit.edu>,
"'dturn@mit.edu'"
<dturn@mit.edu>, E-Zone <E-Zone@mit.edu>,
"'e19site@mit.edu'"
<e19site@mit.edu>,
"'gwolf@mit.edu'" <gwolf@mit.edu>,
"'hallisey@mit.edu'" <hallisey@mit.edu>, "'ilf@mit.edu'" <ilf@mit.edu>,
"'joconor@mit.edu'" <joconor@mit.edu>,
"'kshooter@mit.edu'"
<kshooter@mit.edu>,
"'lharris@MIT.EDU'" <lharris@mit.edu>,
"'mbowers@mit.edu'" <mbowers@mit.edu>, "'mjk@mit.edu'" <mjk@mit.edu>,
"'narbonne@MIT.EDU'" <narbonne@mit.edu>,
"'opsnote@mit.edu'"
<opsnote@mit.edu>,
"'wbarrett@mit.edu'" <wbarrett@mit.edu>,
"'shutdowns@mit.edu'" <shutdowns@mit.edu>, RM-Coach <rm-coach@mit.edu>,
RM-Support <RM-Support@mit.edu>,
"'dmcgreal@mit.edu'" <dmcgreal@mit.edu>,
"'lsanto@mit.edu'" <lsanto@mit.edu>,
"'sfrankel@mit.edu'"
<sfrankel@mit.edu>,
"'joanf@mit.edu'" <joanf@mit.edu>, "'dshea@mit.edu'"
<dshea@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Tue, 25 Nov 2003 12:59:14 -0500
> To: cschultz@mit.edu; dlking@mit.edu; donnab@MIT.EDU; dreid@mit.edu;
> dshea@mit.edu; dturn@mit.edu; E-Zone; e19site@mit.edu; gwolf@mit.edu;
> hallisey@mit.edu; ilf@mit.edu; joconor@mit.edu; kshooter@mit.edu;
> lharris@MIT.EDU; mbowers@mit.edu; mjk@mit.edu; narbonne@MIT.EDU;
> opsnote@mit.edu; wbarrett@mit.edu; shutdowns@mit.edu; RM-Coach;
> RM-Support; dmcgreal@mit.edu; lsanto@mit.edu; sfrankel@mit.edu;
> joanf@mit.edu; dshea@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. E19 - Hot/Cold Domestic/Lab Process Water Shutdown
> Request
>
>
The following hot/cold domestic/lab process/de-ionized water shutdown
request for Bldg. E19 on Monday, December 29, 2003. Would you please let me
know whether this does or does not meet with your approval.
Thanks very much.
Andrea Nichols
Repair and Maintenance
8-7872
> Status: Normal
> Building: E19 - entire building
> Date: 12/29/2003
> Day: Monday
> Time: 7 AM - 3 PM
> System: Hot/Cold Domestic/Lab Process/De-ionized Water
> Duration: 8 hours
> Reason:
> To replace 6" sewer drain in basement.
>
> Effect:
> Loss of hot/cold domestic water. This means that no toilets, bathroom,
> kitchen sink faucets or drinking fountains will be operational during the
> shutdown period. Loss of hot/cold lab process water. This means that lab
> sink faucets will not be operational during the shutdown period. Loss of
> de-ionized water to all labs for lab equipment in E19 during the shutdown
> period.
>
>