[70064] in Hotline Meeting
Bldg. E19 - Revised Exhaust-Laboratory and Exhaust-General Air Sh
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Tue Nov 25 12:14:08 2003
Message-ID: <568F0AEE7A57D511923900508B55645103D71DA0@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'donnab@MIT.EDU'" <donnab@MIT.EDU>, "'dreid@mit.edu'" <dreid@MIT.EDU>,
E-Zone <E-Zone@MIT.EDU>, "'e19site@mit.edu'" <e19site@MIT.EDU>,
"'gwolf@mit.edu'" <gwolf@MIT.EDU>,
"'shutdowns@mit.edu'"
<shutdowns@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Tue, 25 Nov 2003 12:09:44 -0500
> To: donnab@MIT.EDU; dreid@mit.edu; E-Zone; e19site@mit.edu;
> gwolf@mit.edu; shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. E19 - Revised Exhaust-Laboratory and Exhaust-General
> Air Shutdown
>
>
The following revised exhaust-labatory and exhaust-general air shutdown
request for Bldg. E19 - entire 5th floor which would include the autoclave
is for your information. If you have any questions about this, please
contact Hugh Colasacco at x2-4981.
Thank you.
Andrea Nichols
Repair and Maintenance
8-7872
> Status: Normal
> Building: E19 - 5th floor
> Date: 11/26/2003
> Day: Wednesday
> Time: 7:30 AM - 9:30 AM
> System: Exhaust-laboratory, exhaust-general air
> Duration: 2 hours1
> Reason:
> Change belts and sheaves on exhaust fans.
>
> Effect:
> Loss of general exhaust air in E19 5th floor and exhaust-laboratory air in
> the Autoclave during the 2-hour shutdown period.
>
>