[70068] in Hotline Meeting
Bldgs. 10, 7 and 3 Extended Low Pressure Steam Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Tue Nov 25 13:42:23 2003
Message-ID: <568F0AEE7A57D511923900508B55645103D71DA3@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: C-Zone <C-Zone@MIT.Edu>, Cust-Coach <cust-coach@MIT.Edu>,
"'dfucillo@mit.edu'" <dfucillo@MIT.Edu>,
"'dhelman@mit.edu'"
<dhelman@MIT.Edu>,
"'emmarogers@mit.edu'" <emmarogers@MIT.Edu>,
"'esdeb@mit.edu'" <esdeb@MIT.Edu>,
"'granvill@mit.edu'"
<granvill@MIT.Edu>,
"'graposa@mit.edu'" <graposa@MIT.Edu>,
"'jhlyons@mit.edu'" <jhlyons@MIT.Edu>,
"'jobrien@mit.edu'"
<jobrien@MIT.Edu>,
"'jrosoko@mit.edu'" <jrosoko@MIT.Edu>,
"'kates@mit.edu'" <kates@MIT.Edu>, "'lsc@mit.edu'" <lsc@MIT.Edu>,
"'mdhinkle@mit.edu'" <mdhinkle@MIT.Edu>,
"'mleen@mit.edu'"
<mleen@MIT.Edu>, "'ndk@mit.edu'" <ndk@MIT.Edu>,
"'rrhonda@mit.edu'"
<rrhonda@MIT.Edu>,
"'ryan@mit.edu'" <ryan@MIT.Edu>,
"'schedule@mit.edu'"
<schedule@MIT.Edu>,
"'sdl-adm-lib@mit.edu'" <sdl-adm-lib@MIT.Edu>,
"'tkeim@mit.edu'" <tkeim@MIT.Edu>, "'jgk@mit.edu'" <jgk@MIT.Edu>,
"'shutdowns@mit.edu'" <shutdowns@MIT.Edu>,
"'lordjim@mit.edu'"
<lordjim@MIT.Edu>,
"'kimball@mit.edu'" <kimball@MIT.Edu>,
"'laugh@mit.edu'" <laugh@MIT.Edu>, "'jchume@mit.edu'" <jchume@MIT.Edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Tue, 25 Nov 2003 13:41:05 -0500
> To: C-Zone; Cust-Coach; dfucillo@mit.edu; dhelman@mit.edu;
> emmarogers@mit.edu; esdeb@mit.edu; granvill@mit.edu; graposa@mit.edu;
> jhlyons@mit.edu; jobrien@mit.edu; jrosoko@mit.edu; kates@mit.edu;
> lsc@mit.edu; mdhinkle@mit.edu; mleen@mit.edu; ndk@mit.edu;
> rrhonda@mit.edu; ryan@mit.edu; schedule@mit.edu; sdl-adm-lib@mit.edu;
> tkeim@mit.edu; jgk@mit.edu; shutdowns@mit.edu; lordjim@mit.edu;
> kimball@mit.edu; laugh@mit.edu; jchume@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldgs. 10, 7 and 3 Extended Low Pressure Steam Shutdown
> Request
>
>
The following extended low pressure steam shutdown request for Bldgs. 10 -
All perimeter rooms north of passenger elevators (towards 13); 7 - 403, 404
and 3 - 402, 412, 401, 403, 405, 409, 411, 413 and 415 now on Wednesday,
December 3 and Thursday, December 4 is for your information and comment.
Would you please let me know whether these new dates and times do or do not
meet with your approval.
Thank you again for your time.
Andrea Nichols
Repair and Maintenance
8-7872
> Status: Normal
> Building: 10 - all perimeter rooms North of passengr elevators (towards
> 13); 7 - 403, 404, 3 - 402, 412, 401, 403, 405, 409, 411, 413, 415
> Date: 12/3/2003
> Day: Wednesday
> Time: 6 AM - 9 AM
> System: Bldg. 10 Horseshoe Steam Loop/ Low Pressure steam/heating steam;
> also 3 - CV2
> Duration: 3 hours each day for 2 days
> Reason:
> Tying in new perimeter fin tube radiation in 10-370.
>
> Effect:
> Loss of low pressure steam (steam heat) in the above-listed rooms during
> the 2-day/3 hour per day shutdown period.
>
>