Bldg. 4 - Chilled Water/Supply Cooling Shutdown Request

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed Jul 3 12:07:37 2002

Message-ID: <568F0AEE7A57D511923900508B556451012321C1@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'bales@mit.edu'" <bales@mit.edu>, C-Zone <C-Zone@mit.edu>,
        "'chemistryhq@mit.edu'" <chemistryhq@mit.edu>,
        "'cod@mit.edu'"
	 <cod@mit.edu>,
        "'fabianaj@mit.edu'" <fabianaj@mit.edu>,
        "'frc@mit.edu'"
	 <frc@mit.edu>, "'ghughes@mit.edu'" <ghughes@mit.edu>,
        "'glabonte@mit.edu'" <glabonte@mit.edu>,
        "'glwilson@MIT.EDU'"
	 <glwilson@mit.edu>,
        "'graham@mit.edu'" <graham@mit.edu>,
        "'jcentor@mit.edu'" <jcentor@mit.edu>,
        "'lechtman@mit.edu'"
	 <lechtman@mit.edu>,
        "'lkn@mit.edu'" <lkn@mit.edu>, "'mhankin@mit.edu'"
	 <mhankin@mit.edu>,
        "'mwelch@mit.edu'" <mwelch@mit.edu>,
        "'rberlin@mit.edu'" <rberlin@mit.edu>,
        "'rjwilk@mit.edu'"
	 <rjwilk@mit.edu>,
        "'rrhonda@mit.edu'" <rrhonda@mit.edu>,
        "'schedule@mit.edu'" <schedule@mit.edu>,
        "'serotek@mit.edu'"
	 <serotek@mit.edu>,
        "'sralston@mit.edu'" <sralston@mit.edu>,
        "'staton@mit.edu'" <staton@mit.edu>, "'umans@MIT.EDU'" <umans@mit.edu>,
        "'wganger@mit.edu'" <wganger@mit.edu>,
        "'shutdowns@mit.edu'"
	 <shutdowns@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Wed, 3 Jul 2002 12:07:31 -0400 
MIME-Version: 1.0
Content-Type: text/plain

> To: 	bales@mit.edu; C-Zone; chemistryhq@mit.edu; cod@mit.edu;
> fabianaj@mit.edu; frc@mit.edu; ghughes@mit.edu; glabonte@mit.edu;
> glwilson@MIT.EDU; graham@mit.edu; jcentor@mit.edu; lechtman@mit.edu;
> lkn@mit.edu; mhankin@mit.edu; mwelch@mit.edu; rberlin@mit.edu;
> rjwilk@mit.edu; rrhonda@mit.edu; schedule@mit.edu; serotek@mit.edu;
> sralston@mit.edu; staton@mit.edu; umans@MIT.EDU; wganger@mit.edu;
> shutdowns@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldg. 4 - Chilled Water/Supply Cooling Shutdown Request
> 
> 
The following chilled water/supply cooling shutdown request for Bldg. 4 -
250, 252, 260, 270, 243, 249, 253, 255, 257, 259, 261, 265 and 273 on
Tuesday, 7/9 and Wednesday, 7/10 is for your information and comment.  Would
you please let me know whether this does or does not meet with your
approval.

Thanks very much.

Andrea Nichols
Repair and Maintenance
8-7872

> Status: Normal
> Building: 4 - 250, 252, 260, 270, 243, 249, 253, 255, 257, 259, 261, 265
> and 273 
> Date: 7/9/2002
> Day: Tuesday
> Time: 5:30 AM - 9:00 AM each day
> System: Chilled Water
> Duration: 3 1/2 hours each day for 2 days
> Reason: 
> Cut/cap piping back to main for 249 through 253 renovation. *Please note -
> Wednesday's shutdown is provisional.
> 
> Effect: 
> Loss of chilled water (air conditioning) and supply cooling (via ceiling
> supply fans) durng the shutdown period.
> 
> 