[53328] in Hotline Meeting
Emergency shutdown for building 24 on 1/5/01
daemon@ATHENA.MIT.EDU (Dawn Simonelli)
Fri Jan 5 12:24:14 2001
Message-Id: <82F0D564C5ADD31180EF00508B556451D2BCDC@PLANT.MIT.EDU>
From: Dawn Simonelli <dsimone@PLANT.MIT.EDU>
To: andreab@MIT.EDU, B-Zone <B-Zone@MIT.EDU>, cschultz@MIT.EDU,
Cust-Coach
<cust-coach@MIT.EDU>, dcairns@MIT.EDU, devries@MIT.EDU,
dturn@MIT.EDU, ecarl@MIT.EDU, esico@MIT.EDU, hallisey@MIT.EDU,
opsnote@MIT.EDU, politano@MIT.EDU, pszenny@MIT.EDU, radams@MIT.EDU,
schedule@MIT.EDU, sfalconi@MIT.EDU, wendell@MIT.EDU, shutdowns@MIT.EDU
Cc: shutdown@plant.mit.edu
Date: Fri, 5 Jan 2001 12:24:03 -0500
Mime-Version: 1.0
Content-Type: text/plain
> To: andreab@mit.edu; B-Zone; cschultz@mit.edu; Cust-Coach;
> dcairns@mit.edu; devries@mit.edu; dturn@mit.edu; ecarl@mit.edu;
> esico@mit.edu; hallisey@mit.edu; opsnote@mit.edu; politano@mit.edu;
> pszenny@mit.edu; radams@mit.edu; schedule@mit.edu; sfalconi@mit.edu;
> wendell@mit.edu; shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Emergency shutdown for building 24 on 1/5/01
>
>
The following emergency shutdown for building 24 on 1/5/01 is for your
information.
Thank you
Dawn Simonelli
> Status: Critical
> Building: 24
> Date: 1/5/01
> Day: Friday
> Time: 12:45 pm- 1:15pm
> System: Hot and Cold water
> Duration: 1/2 hour
> Reason:
> They are trying to isolate a leak
>
> Effect:
> This will effect all hot and cold building water.
>
>