[205] in Enterprise Print Delivery Team

home help back first fref pref prev next nref lref last post

Re: Next Status Report

daemon@ATHENA.MIT.EDU (Kenneth Bruggeman)
Mon May 8 10:23:19 2000

Message-Id: <v03020900b53c730b2133@[18.80.2.81]>
In-Reply-To: <10005051612.AA29755@MIT.EDU>
Mime-Version: 1.0
Content-Type: text/plain; charset="us-ascii"
Date: Mon, 8 May 2000 10:14:07 -0400
To: "David F. Lambert" <LAMBERT@MITVMA.MIT.Edu>,
        Enterprise Printing Delivery Project Team <printdel@MIT.EDU>
From: Kenneth Bruggeman <kiplb@MIT.EDU>

>Folks,
>
>I'm a bit overdue with our status report, and my past "predictions"
>regarding goals have not been as accurate as we need them to be
>for our reports.  Therefore, I'd like to ask that you each send
>your accomplishments since the last report and goals for the next
>three weeks to the printdel list.  To jog your memory, I'm including
>the last status report below.  Please provide your input ASAP - but
>no later than the end of the day on Monday.  Thanks in advance!
>
>-Dave



From Kip.....

Accomplishments for the past period:

- Determined costs for the current system for equipment, maintenance, and
consumables.
- Submitted explanation of these costs for the draft of the current model
document.


Goals for the coming period:
- Complete the analysis of the current business model & costs.
- Begin to analyse equipment, maintenance, and consumable costs for the new
system based on current and expected volumes.
- Determine trade-in value of old equipment to IBM or other (broker).
- Solicit competitive vendor bid on equipment for justification of new IPM
acquisitions.




home help back first fref pref prev next nref lref last post