>Folks,
>
>I'm a bit overdue with our status report, and my past "predictions"
>regarding goals have not been as accurate as we need them to be
>for our reports. Therefore, I'd like to ask that you each send
>your accomplishments since the last report and goals for the next
>three weeks to the printdel list. To jog your memory, I'm including
>the last status report below. Please provide your input ASAP - but
>no later than the end of the day on Monday. Thanks in advance!
>
>-Dave
From Kip.....
Accomplishments for the past period:
- Determined costs for the current system for equipment, maintenance, and
consumables.
- Submitted explanation of these costs for the draft of the current model
document.
Goals for the coming period:
- Complete the analysis of the current business model & costs.
- Begin to analyse equipment, maintenance, and consumable costs for the new
system based on current and expected volumes.
- Determine trade-in value of old equipment to IBM or other (broker).
- Solicit competitive vendor bid on equipment for justification of new IPM
acquisitions.