Project Name: IS Server Business
Project Leader: Joanne Hallisey
Report Date:3/7/02
Submitted by: Joanne Hallisey
URL: http://web.mit.edu/is/discovery/isserver

Accomplishments (what did we accomplish in the last period?)

- Followed up survey with interviews as needed
- Collated survey data and began analysis
- Collected peer school information
- Continued documenting existing services
- Met with Cecilia Talamantes to discuss existing financial models
- Began price and service comparison to outside vendors


Goals (What are we planning to accomplish in the next period?)

- Additional interviews if clarification is needed
- Begin to draft service matrix
- Follow up with visits to schools with server operations that interest team
- Begin Financial analysis
- Continue to build report

Have there been any developments that may impact the scope or schedule?

- good progress made on survey, but we still struggle with finding 
time to do the work outside of the project meeting time.

Do we need any additional information from the client, 
stakeholders,sponsor? - not yet

Issues/Key Learnings


Team Dynamics
Good.