3rd barton bi-weekly report

daemon@ATHENA.MIT.EDU (Carl Jones)
Wed Sep 13 16:17:43 2000

Message-Id: <200009132017.QAA20398@torill.mit.edu>
To: magellan@MIT.EDU
Cc: stc-lib@MIT.EDU, 3rdbc@MIT.EDU, 3rdbarton@MIT.EDU, raycheng@MIT.EDU
Date: Wed, 13 Sep 2000 16:17:34 -0400
From: Carl Jones <carlj@torill.mit.edu>
Reply-To: carlj@MIT.EDU

Project Name: Third Barton Project (Project to find a replacement
Library Management System)
Project Management Team: Nina Davis-Millis, Joan Kolias, Carl Jones
Report Date: Sept. 13, 2000
URL: http:/macfadden.mit.edu:9500/c3/3dbarton

Accomplishments Past Period:

- Completed week-long vendor demos for the two finalists. These
  took place at the end of July and first week of August.

- Held de-briefing sessions with all functional areas, as well as
  feedback session with SAP group participants, and Ray Cheng from the
  MIT Auditors office.

- Formalized contents of staff de-briefing sessions into structured  
documents.

- Met with Asst. Director of Technology Planning  and  
Administration, Eric Celeste, to
  discuss  report and final vendor recommendation to Library  
Steering Committe.

- Draft of final vendor recommendation submitted to Library Steering  
Committee.


Goals for the coming period:

- Meet with Steering Commitee to discuss draft vendor recommendation  
report.

- Complete revisions and Submit final vendor recommendation to
  Steering Committee.

- Upon Steering Committe's approval, hold Town Meeting with Library
  staff to announce vendor choice.

- Begin work on next phase: migration and implementation issues.


Issues:

- Either of the systems demonstrated will have significant staffing
  implications for the Systems Office group that will administer and
  maintain the new library management system.


Team Dynamics:

- We're looking forward to having an official vendor for the new
  library management system.

home help back first fref pref prev next nref lref last post