IS Operational Plan Alive, 12/15/1999

daemon@ATHENA.MIT.EDU (Tim McGovern)
Thu Dec 16 11:33:14 1999

Mime-Version: 1.0
Content-Type: text/plain; charset="us-ascii"
Message-Id: <v04020a02b47ec2c7e250@[18.152.1.21]>
Date: Thu, 16 Dec 1999 11:33:08 -0500
To: magellan@MIT.EDU
From: Tim McGovern <tjm@MIT.EDU>
Cc: iswork@MIT.EDU

Project Name:     IS Operational Plan Alive!
Project Leaders:  Tim McGovern
Report Date:      December 15, 1999
Project Notebook: http://web.mit.edu/is/discovery/iswork/

Goals listed in last report
1  Develop a more detailed deliverables breakdown structure (DBS) to estimate
	project duration/schedule
2  Gather information on information to be maintained from Project
	Database process (current)
3  Integrate Operational Plan and Projects information
4  Develop data model for project..begin vetting process for data model
5  Develop/discuss architecture alternatives
6  Schedule project sponsor checkin

Accomplishments past period
-  DBS still evolving
-  Mapped data from existing Project DB, and from Operational Plan.
   Integrated data elements from both sources into:
	http://web.mit.edu/is/discovery/iswork/dataDictionary.pdf
-  Drafted ER Diagram at a conceptual level:
	http://web.mit.edu/is/discovery/iswork/datamodel.pdf
-  Discussed architecture, and am ready to produce proposed architecture
-  Met with project sponsors to review all of the above products, and decided
	next steps.

Goals for the coming period (or so)
-  Schedule executive sponsor check-in to ensure alignment on requirements
-  Complete diagramming of design/architecture, and schedule ITIT check-in.
-  Confirm data modelling session for Jan. 7 with all participants.
-  Request ITLT checkout session for Feb. 3.

Issues
-  Nothing new this fortnight.

Key learnings
-  N/A

Team dynamics
-  N/A

Additional comments
-  Nothing