Project Name:	Web Reporting
Project Leader:	Greg Anderson, Jonathan Venezian
Report Date:	Jan. 28, 1999

Accomplishments past period 
- Team met with Greg, Suzana to kick off effort again 
- Team determined that a prototype needed to be built based on learnings so far 
- Decision that project will have multiple sponsors, probably an
administrative department and an academic department head
- Met with data warehouse rep to discuss prototype feed into warehouse 

Goals for the coming period 
- Map out prototype architecture 
- Understand and document access control list from AFS to roles in warehouse 
- Determine pages to be tracked in prototype period
- Define standard reports for users

Issues 
- none

Key learnings 
- above

Team dynamics 
- Steve Turner is now a part of the team with a warehouse hat 

Additional comments 
- We're glad to be moving again!! 

----------------------------------------------------------------------