Project Name:     IS Operational Plan Alive!
Project Leaders:  Tim McGovern
Report Date:      December 1, 1999
Project Notebook: http://web.mit.edu/is/discovery/iswork/ ** under construction

Goals listed in last report

*** This is the first report for this project
*** since the official launch on 11/26/1999.

Accomplishments past period
-  Project launched
-  Gathered materials containing information to be maintained from
	Strategic Planning process
-  Began process of mapping/modelling data for input to design effort

Goals for the coming period (or so)
-  Develop a more detailed deliverables breakdown structure to estimate
	project duration/schedule
-  Gather information on information to be maintained from Project
	Database process (current)
-  Integrate Operational Plan and Projects information
-  Develop data model for project..begin vetting process for data model
-  Develop/discuss architecture alternatives
-  Schedule project sponsor checkin

Issues
-  Time...time...time  Although I'm getting help from resources around the
	organization, realistically, there's probably on the order of 10%
	of me to allocate to this project, so progress is VERY slow.

Key learnings
-  Nothing yet, still getting started

Team dynamics
-  Current team is me alone, I'm doing fine, thanks for asking!!!

Additional comments
-  Nothing