Long Jobs

daemon@ATHENA.MIT.EDU (Mike Barker)
Wed Jan 27 09:43:06 1999

Date: Wed, 27 Jan 1999 07:30:00 -0500
To: magellan@MIT.EDU
From: Mike Barker <mbarker@MIT.EDU>

Project Name: Long Jobs
Project Leader: Mike Barker
Report Date: Jan. 28, 1999

Accomplishments past period

1.  Mike Barker sent out a sizing memo and a remaining steps memo.
2.  A "re-kickoff" meeting was held 1/25/1999.  Anne Salemme, Ted, Greg 
Anderson, Bill Cattey, Mike Barker, Bob Basch, Naomi Schmidt, Vijay Kumar 
attended.

Goals for the coming period

1.  Anne will write up where we are and requirements
2.  Bob will turn on the prototype under his desk
3.  Ted will draft administration requirements
4.  Naomi will begin planning a "focus group" for faculty, etc. re 
direction, sizing, etc.

Issues

1.  I am concerned that the "prototype" being discussed for summer probably 
means different things to different people.
2.  There are still calls to "harvest spare cycles"

Raised at the meeting and largely unanswered:
1.  Sponsorship?
2.  Relative value?
3.  Commitment?
4.  Leverage?
5.  Technical Design?

The last item seems to be where we are focusing our efforts.

Key learnings

Team dynamics

Additional comments