Project Name:     Class Participants Lists
Project Leaders:  Tim McGovern
Report Date:      July 14, 1999
Project Notebook: http://web.mit.edu/is/discovery/grouper/

Goals listed in last report
1. Confirm commitments for Delivery/Integration work (carryover)
2. Gather feedback from sponsors
3. Begin User Interface design process
4. Complete process of verbal check-ins
5. Prepare (if necessary) for appointment with ITIT for final check-in
6. Make appointment with ITLT (if necessary) for check-in

Accomplishments past period
-  Checkin with Delivery completed; checkin scheduled with Integration for
7/19;
   checkin in User Accounts completed.
-  Sponsor checkin still pending
-  2 UI Design sessions, more scheduled, major approaches worked out
-  Still pondering ITLT checkin

Goals for the coming period
-  Meet with ITIT and complete that checkin
-  Continue to build strawman User Interface
-  Contact small number of faculty to sanity check UI
-  Continue work on outstanding issues where possible
-  Begin work on technical pieces based on UI and Moira-based design
-  Formally transition project into Delivery/Integration area

Issues
-  http://web.mit.edu/is/discovery/grouper/issues.html

Key learnings
-  Not too much new this fortnight!

Team dynamics
-  It's getting good...

Additional comments
-  N/A